FOR WEEK OF JUNE 21, 2020

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, and SR 70. Crews are also working on the retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 301 at Erie Road/Old Tampa Highway: Construction project: Crews are making improvements to the intersection. Motorists should expect daytime and nighttime lane closures on westbound US 301 from 12 p.m. to 5:30 a.m., and eastbound on US 301 from 7 p.m. to 2 p.m. while crews are working. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 19 from US 41 to Terra Ceia Road: Construction project: Crews are resurfacing the roadway, improving drainage and constructing sidewalk. Expect daytime single lane closures between 9 a.m. and 4 p.m. and nighttime/overnight lane closures between 7 p.m. and 6 a.m. throughout construction. AJAX Paving Industries of Florida is the contractor. Expected completion is early 2021.

SR 684/Cortez Road from 123rd Street W to 119th Street W and from 123rd Street W to 86th Street W: Construction project: Crews are realigning the intersection of  SR 684/Cortez Road and 119th Street W, resurfacing the roadway, improving drainage, constructing sidewalk and installing new highway lighting. Expect nighttime/overnight lane closures from 10 p.m. to 6 a.m. on SR 684/Cortez Road and on 119th Street W (both north and southside). Daytime lane closures from east of 119th Street W to 86th Street W within the four-lane section of SR 684/Cortez Road are expected from 8 a.m. to 4 p.m. over the next few weeks. AJAX Paving Industries of Florida, LLC is the contractor. Expected completion is late fall 2020.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage and installing new highway lighting and landscaping. Traffic has been shifted to the southside of SR 64 with one 10-foot lane in each direction. The speed limit on State Road 64 has been reduced to 25 mph within the construction zone. IBT Construction is the contractor. Expected completion is summer 2020.

SR 64 eastbound at 11th Street W: Construction project: Crews are resurfacing the roadway, constructing sidewalk, improving lighting and signalization, and installing new signing and pavement markings. Expect nighttime/overnight single lane closures on westbound SR 64 from 7:30 p.m. to 6 a.m. while crews are working. Expect single lane closures on eastbound SR 64 from 9 a.m. to 4 p.m. and from 7 p.m. to 6 a.m. while crews are working. American Lighting and Signalization, LLC is the contractor. Expected completion is summer 2020.

SR 64 over Perico Bayou and Palma Sola Bay: Construction project: Crews are working on the bridges. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Sidewalk closures are not expected during construction. Olympus Painting Contractor, Inc. is the contractor. Expected completion is fall 2020.

 

SARASOTA COUNTY

I-75 at SR 681, SR 758/Bee Ridge Road, and SR 780/Fruitville Road: Maintenance project: This week, crews are installing new components on the high mast light poles. The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is late May 2020; weather permitting.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation, and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a six-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is fall 2020. The contractor is IBT Construction LLC.

US 41 (Venice Bypass) from Center Road to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb and sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. The contractor is Bergeron Land Development, Inc. Expected completion is spring 2021. 

US 41 from First Street to Boulevard of the Arts, and on Fruitville Road from US 41 to Cocoanut Avenue: Construction project: Crews are constructing a roundabout at US 41 and Fruitville Road, a 12-foot multi-use trail on the west side of US 41 and a variable-width sidewalk on the east side of US 41; replacing existing underground drainage and utility structures, and installing new LED streetlights and landscaping. Other improvements include raised pedestrian refuge islands and a HAWK pedestrian signalization system. Use caution and watch for changes in the traffic pattern. Wright Construction, Inc. is the contractor. Expected completion is fall 2020.

US 41 from River Road to Woodmere Park Boulevard: Construction project: Crews are constructing sidewalk and bus shelter pads; installing guardrail and lighting and improving drainage. Motorists should expect daytime lane closures from 9 a.m. to 4 p.m. and nighttime lane closures from 7 p.m. to 6 a.m. while crews are working. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2020.

US 41 from Blackburn Point Road to Preymore Street: Construction project: Crews are resurfacing the roadway, replacing the US 41 northbound bridge over North Creek, improving drainage, constructing sidewalk, and installing new highway lighting. Expect nighttime/overnight northbound lane closures from 6 p.m. to 6 a.m. and nighttime/overnight southbound lane closures from 6:30 p.m. to 9:30 a.m. Northbound traffic will shift to one of the southbound lanes, reducing traffic to one lane each direction. The traffic shift is expected to be in place for approximately eight months while crews reconstruct the northbound bridge over North Creek. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 789/John Ringling Boulevard at Coon Key: Maintenance permit project: Crews for the City of Sarasota are installing a water main. Motorists should expect westbound single lane closures through early June while crews are working. Use caution and expect possible delays.