FOR WEEK APRIL 4, 2021
Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.
As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.
MANATEE COUNTY
I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, and median and drainage work on SR 70.
Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Sacyr Construction USA, LLC.
I-275 at US 19 (Exit 5): Construction project: Crews will remove the existing high mast lighting systems and replace with conventional lighting systems. This week, crews will work on the light pole foundations. Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Highway Safety Devices.
I-275 at US 41 (Exit 2): Construction project: Crews will remove the existing high mast lighting systems and replace with conventional lighting systems. This week, crews will install conduit. Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Highway Safety Devices.
I-275 southbound ramp at the juncture of I-75 north: Construction maintenance: Crews will be performing warranty repair work on the I-275 southbound ramp to the I-75 northbound ramp on Saturday and Sunday, April 3rd and 4th, from 7 a.m. to 5 p.m. The work will only require a shoulder closure so traffic should not be impacted, but please use extra caution in the high-speed, high traffic roadway.
US 301 and 13th Avenue West: Construction project: crews will be working in the area adding a right turn lane, milling and resurfacing, base work, drainage improvements, curbs and gutters, traffic signals, lighting, highway signing, pavement marking, sidewalks, and adding Intelligent Transportation System improvements.
The contractor is MSB Services LLC. Expected completion is late spring 2021.
SR 64 at Greyhawk Boulevard/Pope Road: Construction project: Construction of a roundabout at SR 64 and Greyhawk Boulevard/Pope Road includes installing pedestrian activated crossings on all legs of the roundabout, adding lighting and landscaping, and installing a new traffic signal and crosswalks at SR 64 and 117th Street east. The contractor is Watson Civil Construction, Inc. Expected completion is fall 2021, weather permitting.
SARASOTA COUNTY
US 41 at Gulfstream Avenue Roundabout: Construction project: Crews will work within the right-of-way, medians, driveways and throughout the project limits. Activities include:
Detours and lane closures will be in place during various phases of the project. Initial pre-phase work involves building temporary roadway for use during subsequent phases. This work will not impact existing travel lane configuration.
Construction activities will take place during the daytime and occasionally during nighttime hours. Expect noise from backup alarms, construction equipment, pumps, and power tools during daytime and nighttime operations.
During construction, the speed limit will be reduced to 25 mph on US 41 and Gulfstream Avenue. Speeding fines are doubled in the construction area when workers are present. Motorists are urged to use caution and watch for workers, construction vehicles, pickup trucks and other construction equipment within the work zone and entering or exiting the travel lanes. Expected completion is early fall 2022. The contractor is Russell Engineering, Inc.
US 41 southbound in front of Sarasota Memorial Hospital at Hillview Street: Construction maintenance: crews will be replacing the manhole on US 41. Motorists should expect a lane closure on Monday, April 5, from 9 a.m. to 12 noon. Please use caution in the high traffic area.
US 41 from Blackburn Point Road to Preymore Street: Construction project: Work includes resurfacing the roadway, improving drainage, constructing sidewalks, replacing the US 41 northbound bridge over North Creek, and installing new highway lighting along the three-mile project.
Bergeron Land Development, Inc. is the contractor. Expected overall project completion is spring 2021.
US 41 (Venice Bypass) from Center Road to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway, replacing traffic signals, installing new pavement markings and signage; installing concrete curb and sidewalks; improving new drainage; and installing new highway lighting. Use caution and watch for changes in the traffic pattern. The contractor is Bergeron Land Development, Inc. Expected completion is spring 2021.
SR 789 at New Pass Bridge, Longboat Key: Bridge construction: The improvement project includes structural, mechanical, and electrical repairs to the bridge. Two lanes of traffic will be maintained during the construction but please use caution in the area as lane patterns will be adjusted. If nighttime bridge closures are required, they will be done between 3 a.m. and 5 a.m. with no detour longer than 30 minutes.
The contractor is Quinn Construction. Completion is expected by summer 2021.