Traffic-Watch

FOR THE WEEK OF FEBRUARY 14, 2021

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, and SR 70.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Sacyr Construction USA, LLC.

I-275 northbound prior to the toll plaza (between MM 5.5 and 5.9): Maintenance project:  Crews will be repairing an over-lane sign before the Skyway Bridge toll plaza.  Expect a left lane closure from 11 p.m. to 5 a.m. The contractor is DBi Services.

I-275 at US 19 (Exit 2): Construction project: Crews will remove the existing high mast lighting systems and replace with conventional lighting systems.  Variable message signs will be in place to alert drivers that work is underway. Estimated completion is mid-2021. The contractor is Highway Safety Devices.

US 41 at the Hernando Desoto Bridge: Bridge maintenance: Crews will be making repairs from Tuesday, February 16, through Thursday, February 18, 2021.  Motorists should expect intermittent lane closures both north and southbound from 8 p.m. to 4 a.m. The contractor is DBi Services.

US 41/ US 301 and 13th Avenue West: Construction project: crews will be working in the area adding a right turn lane, milling and resurfacing, base work, drainage improvements, curbs and gutters, traffic signals, lighting, highway signing, pavement marking, sidewalks, and adding Intelligent Transportation System improvements. On 13th Avenue west, there should be no daytime lane closures from 6 a.m. to 7 p.m. so traffic should be mostly unaffected. On 13th Avenue west, the right sidewalk leading up to the corner of US 301 will be closed. A crosswalk will be installed prior to the intersection or use the alternate side of the street or an alternate route. The contractor is MSB Services LLC. Expected completion is late spring 2021.

US 301 from 61st Street east to Old Tampa Road: Construction maintenance: Crews will be making asphalt repairs Monday, February 15, through Thursday, February 18, 2021, from 8 p.m. to 5:30 a.m. Lane closures will be intermittent both east and west bound.  The contractor is Midwestern Construction. 

US 19 from US 41 to Terra Ceia Road: Construction project: work includes resurfacing the roadway, improving drainage and constructing a sidewalk. Work is in the final stages of completion. Daytime single-lane closures between 9 a.m. and 4 p.m. and overnight lane closures between 7 p.m. to 6 a.m. are allowed throughout construction. AJAX Paving Industries of Florida is the contractor. Expected completion is early 2021.

SR 684 / Cortez Road from 123rd Street W to 119th Street W and from 123rd Street W to 86th Street W: Construction project: work includes realigning the intersection of SR 684/Cortez Road and 119th Street west, while also resurfacing the roadway, improving drainage, constructing a sidewalk and installing new highway lighting.  The project is in the final stages of completion with only intermittent lane closures if needed. AJAX Paving Industries is the contractor. Expected completion is first quarter 2021.

SR 64 at Uihlein Road: Construction permit project: There will be intermittent lane closures on both east and westbound lanes through February 21, 2021, from 9 a.m. to 4 p.m. for the construction of a left turn lane, right turn lane, and driveway connection. 

SR 64 at Greyhawk Boulevard/Pope Road: Construction project: Construction of a roundabout at SR 64 and Greyhawk Boulevard/Pope Road includes installing pedestrian activated crossings on all legs of the roundabout, adding lighting and landscaping, and installing a new traffic signal and crosswalks at SR 64 and 117th Street east.  The contractor is Watson Civil Construction, Inc. Expected completion is summer 2021, weather permitting.

 

SARASOTA COUNTY

US 41 Roundabouts at 10th Street and 14th Street:  Construction project:

Motorists are urged to use caution and watch for workers, construction vehicles, pickup trucks and other construction equipment within the work zone and entering or exiting the travel lanes.

Motorist entering the roundabout regardless of direction of travel, are required to YIELD to traffic already within the roundabout and follow roundabout signage and driving conditions.

Permanent speed limit set to 35 mph. Speeding fines are doubled in the construction area when workers are present.

Expect noise from back up alarms, trucks, and construction vehicles throughout the project corridor.

Work is expected during daytime hours, but some activities may require weekend and nighttime work.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a six-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is early winter 2021. The contractor is IBT Construction LLC.

US 41 from Blackburn Point Road to Preymore Street: Construction project: Work includes resurfacing the roadway, improving drainage, constructing sidewalks, replacing the US 41 northbound bridge over North Creek, and installing new highway lighting along the three-mile project.  North and south bound US 41 lanes have returned to two lanes in both directions. Bergeron Land Development, Inc. is the contractor. Expected overall project completion is spring 2021.

US 41 Business at Venice Bypass: Construction permit project: crews will be constructing a driveway connection on the northbound right lane through February 21, 2021, from 9 a.m. to 4 p.m.  Motorists should expect intermittent lane closures.  Please use caution and expect possible delays.

US 41 (Venice Bypass) from Center Road to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway, replacing traffic signals, installing new pavement markings and signage; installing concrete curb and sidewalks; improving new drainage; and installing new highway lighting. Use caution and watch for changes in the traffic pattern. The contractor is Bergeron Land Development, Inc. Expected completion is spring 2021. 

US 41 between north of Tuscola Drive to north of Venice east and Woodmere Street: Construction maintenance: crews will be reshaping and reworking ditches Monday, February 15, through Friday, February 19, 2021, from 7 a.m. to 5 p.m. The contractor will utilize a shoulder closure.  In some areas with limited shoulder, outside lane closures may be required.  Contractor is Midwestern Construction.

US 41 from Panama Drive to 15th Street: Construction permit project: There will be intermittent north and southbound lane closures thru February 29, 2021, from 8 p.m. to 5 a.m.  Project includes median utility work and the construction of a left turn lane and several driveway connections along US 41.  Please use caution and expect possible delays.

SR 758 (Higel/ Shell Avenue) from Little Pond Lane to Somerset Drive on Siesta Key: Construction project: This project will improve drainage, resurface the roadway, and improve the sidewalk and shoulder on Higel Avenue from Little Pond Lane to Somerset.  The contractor is in final stages of completion and project acceptance. Motorists should expect only intermittent lane closures if needed. The contractor is Heavy Civil, Inc.

SR 789 at New Pass Bridge, Longboat Key: Bridge construction: The improvement project includes structural, mechanical, and electrical repairs to the bridge. Two lanes of traffic will be maintained during the construction but please use caution in the area as lane patterns will be adjusted. If nighttime bridge closures are required, they will be done between 3 a.m. and 5 a.m. with no detour longer than 30 minutes.

The contractor is Quinn Construction. Completion is expected by summer 2021.