Nov
15

Traffic Watch for Manatee and Sarasota Counties

Follow-us_-galacticgroup Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF NOVEMBER 17, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is early 2020. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound  I-75. The I-275 southbound ramp to northbound I-75 will remain closed through late November. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the  I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Use caution and watch for changes in the traffic pattern. Expected completion is spring 2020. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, noise walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 301 (State Road 43) from Moccasin Wallow Road to the Hillsborough County Line: Construction project: Watch for daytime shoulder closures as crews install project signs, erosion control devices and begin milling and paving operations. The improvements under this contract consist of milling and resurfacing, super elevation correction, shoulder reconstruction, turnout construction, drainage improvements, shoulder treatment, signing and pavement markings.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. Traffic has been shifted to the southside of SR 64 with one 10 foot lane in each direction. The speed limit on State Road 64 has been reduced to 25 mph within the construction zone. Motorists should expect daytime and nighttime flagging operations at the intersection of SR 64 and Rye Road through Friday, November 8 while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

 

SARASOTA COUNTY

I-75 from Exit 182/N. Sumter Boulevard to Exit 191/N. River Road: Construction project: This project replaces sections of guardrail along the interstate. The contractor is Acme Barricades, L.C.  Expected completion is late 2019.  

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern is in place. South bound traffic will be using the new roadway and north bound traffic is shifted to the west. Be cautious while driving through the transition zones at the south and north ends of the project, while crews are still trying to work on enhancing the roadway striping and signs.
  • The project work zone is shifted to the east side of US 41, pay attention to the travel lanes while entering and leaving the businesses or side streets. No left turns permitted within the project limits, except at the boat ramp, which has an exclusive left turn lane for north bound traffic.
  • Pedestrian pathways are detoured mostly via Cocoanut Avenue while the west side new sidewalk is being installed. Pedestrians are urged to stay away from construction zones where there is no designated pedestrian access.
  • Crews will be working on grinding and removing asphalt from the old roadway between 10th Street and 13th Street on the east side. Noise and dust are expected during the removal of old asphalt. Expect noise from backhoes, concrete saws, jack hammers and material loading into trucks.
  • 11th Street and 13th Street will continue to be closed to through traffic while crews are working on installing drainage pipe and structures. The closures are expected to extend through the end of next week
  • 12th Street is expected to be closed following the work at 11th and 13th Street, for the installation of drainage pipe. Motorists may access to 12th Street via Cocoanut Avenue. Detour signs will be installed to guide motorists around the closure. Existing landscaping and irrigation will be impacted within construction zone.
  • Drainage and grading work will commence at 12th Street and 14th Street. Expect noise from backhoes, pumps, backup alarms and vibration from compaction.
  • Light pole installation is expected at 14th Street. Expect lane closure south bound US 41 south of 14th Street intersection, while crews set the foundation with a crane.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended only for entering traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, November 22. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Seaboard Avenue at US 41 is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. 
  • A traffic switch has been implemented on US 41 from Center Road to Gulf Coast Boulevard shifting traffic east to the existing southbound lanes and median. Two travel lanes in each direction are maintained throughout the project limits, and the speed limit has been reduced to 40 mph. Please use caution when traveling through the project corridor as the demarcated median has narrowed. Vehicles no longer have median access throughout the project limits.
  • Motorists should expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. through Sunday, November 24 as crews perform water main installation activities. 

US 41 from First Street to Boulevard of the Arts, and on Fruitville Road from US 41 to Cocoanut Avenue: Construction project: Crews are constructing a roundabout at US 41 and Fruitville Road, a 12-foot multi-use trail on the west side of US 41 and a variable-width sidewalk on the east side of US 41; replacing existing underground drainage and utility structures, and installing new LED streetlights and landscaping. Other improvements include raised pedestrian refuge islands and a HAWK pedestrian signalization system. Use caution and watch for changes in the traffic pattern. Wright Construction, Inc. is the contractor. Expected completion is fall 2020.

  • Beginning the evening of Sunday, November 17, through the evening of Thursday, November 21, motorists should expect closures of the inside lane of US 41 from First Street to Fifth Street for nighttime work.
  • The week of November 17, motorists should expect intermittent northbound single outside lane closures of US 41 between First Street and Second Street during daytime hours for utility work. There will also be lane closures along Second Street between US 41 and Cocoanut Avenue for utility work. Flaggers will be present to direct traffic along Second Street.

US 41 from River Road to Woodmere Park Boulevard: Construction project: Crews are constructing sidewalk and bus shelter pads; installing guardrail and lighting, and improving drainage. Motorists should expect daytime lane closures from 9 a.m. to 4 p.m. and nighttime lane closures from 7 p.m. to 6 a.m. while crews are working. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2020.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, November 22. Use caution and expect possible delays.

Continue reading
  140 Hits
0 Comments
140 Hits
  0 Comments
Nov
01

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF NOVEMBER 3, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is early 2020. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed through late fall. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning through Wednesday, November 27. Use caution and watch for changes in the traffic pattern. Expected completion is spring 2020. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, noise walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

US 301 (State Road 43) from Moccasin Wallow Road to the Hillsborough County Line: Construction project: Watch for daytime shoulder closures as crews install project signs, erosion control devices and begin milling and paving operations. The improvements under this contract consist of milling and resurfacing, super elevation correction, shoulder reconstruction, turnout construction, drainage improvements, shoulder treatment, signing and pavement markings.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch is expected to be implemented on Monday, November 4. Once implemented, traffic will shift to the southside of SR 64 and the speed limit on State Road 64 will be reduced to 25 mph. Motorists should expect daytime and nighttime flagging operations at the intersection of SR 64 and Rye Road through Friday, November 8 while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

SARASOTA COUNTY

I-75 from Exit 182/N. Sumter Boulevard to Exit 191/N. River Road: Construction project:  This project replaces sections of guardrail along the interstate. The contractor is Acme Barricades, L.C.  Expected completion is late 2019.  

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern is in place. South bound traffic will be using the new roadway and north bound traffic is shifted to the west. Be cautious while driving through the transition zones at the south and north ends of the project, while crews are still trying to work on enhancing the roadway striping and signs.
  • The project work zone is shifted to the east side of US 41, pay attention to the travel lanes while entering and leaving the businesses or side streets. No left turns permitted within the project limits, except at the boat ramp, which has an exclusive left turn lane for north bound traffic.
  • Noise and dust are expected during the removal of old asphalt. Expect noise from backhoes, concrete saws, jack hammers and material loading into trucks.
  • Drainage and grading work continue around the Sunoco and Publix driveways. Entrances to both will be open to traffic by the end of the week. Expect noise from equipment, vibration from compaction and heavy equipment in the area.
  • Night work is expected Monday and Wednesday night for the waterline tie in at 14th Street and Imperial Drive. There will be lane closures north bound and south bound on US 41 north of 14th Street for the tie in. Expect noise from backhoes, pumps and concrete saws.
  • Light pole installation is expected at 10th and 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • Stormwater work will begin at 11th Street the week of November 4th. 11th Street will be closed while work is occurring, and the closure is expected to last one week. Please follow detour route via 12th Street. Subsequent side streets will be closed for storm work in the weeks that follow.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended only for entering traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, November 8. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Seaboard Avenue at US 41 is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route.
  • A traffic switch has been implemented on US 41 from Center Road to Gulf Coast Boulevard shifting traffic east to the existing southbound lanes and median. Two travel lanes in each direction are maintained throughout the project limits, and the speed limit has been reduced to 40 mph. Please use caution when traveling through the project corridor as the demarcated median has narrowed. Vehicles no longer have median access throughout the project limits.

US 41 from First Street to Boulevard of the Arts, and on Fruitville Road from US 41 to Cocoanut Avenue: Construction project: Crews are constructing a roundabout at US 41 and Fruitville Road, a 12-foot multi-use trail on the west side of US 41 and a variable-width sidewalk on the east side of US 41; replacing existing underground drainage and utility structures, and installing new LED streetlights and landscaping. Other improvements include raised pedestrian refuge islands and a HAWK pedestrian signalization system. Use caution and watch for changes in the traffic pattern. Wright Construction, Inc. is the contractor. Expected completion is fall 2020.

  • The week of October 28, motorists should expect possible nighttime lane closures from 9 p.m. to 7 a.m.  During daytime hours, there will be isolated utility excavations in the sidewalk path along US 41 between First Street and Fruitville Road as well as Second Street between US 41 and Cocoanut Avenue.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, November 1. Use caution and expect possible delays.

Continue reading
  217 Hits
0 Comments
217 Hits
  0 Comments
Oct
17

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF OCTOBER 20, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is early 2020. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed through late fall. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, October 20 through Saturday, October 26. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, October 20 through Saturday, October 26. Use caution and watch for changes in the traffic pattern. Expected completion is spring 2020. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, noise walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch is expected to be implemented on Tuesday, October 22.  The speed limit on State Road 64 will be reduced to 25 mph. Motorists should expect right turn lane closures from Rye Road to westbound SR 64 from 9 a.m. to 4 p.m. daily through Friday, October 25 while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

 

SARASOTA COUNTY

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern is in place. South bound traffic will be using the new roadway and north bound traffic is shifted to the west. Be cautious while driving through the transition zones at the south and north ends of the project, while crews are still trying to work on enhancing the roadway striping and signs.
  • The project work zone is shifted to the east side of US 41, pay attention to the travel lanes while entering and leaving the businesses or side streets. No left turns permitted within the project limits, except at the boat ramp, which has an exclusive left turn lane for north bound traffic.
  • Noise and dust are expected during the removal of old asphalt. Expect noise from backhoes, concrete saws, jack hammers and loading into trucks.
  • Night work is expected in about a week or 10 days for the waterline tie in at 14th Street and Imperial Drive. There will be lane closures north bound and south bound on US 41 north of 14th Street for the tie in. Expect noise from backhoes, pumps and concrete saws. This work is expected for 2 nights.
  • Light pole installation is expected at 10th and 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • Storm drainage pipe and structure installation will begin on the east side of US 41. Expect noise from equipment, tools and compaction operation.
  • The right turn lane on westbound 10th Street, east of US 41 is closed. The through lane now serves as a through and right turn lane.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, November 1. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Seaboard Avenue at US 41 is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route.
  • A traffic switch has been implemented on US 41 from Center Road to Gulf Coast Boulevard shifting traffic east to the existing southbound lanes and median. Two travel lanes in each direction are maintained throughout the project limits, and the speed limit has been reduced to 40 mph. Please use caution when traveling through the project corridor as the demarcated median has narrowed. Vehicles no longer have median access throughout the project limits.

US 41 from First Street to Boulevard of the Arts, and on Fruitville Road from US 41 to Cocoanut Avenue: Construction project: Crews are constructing a roundabout at US 41 and Fruitville Road, a 12-foot multi-use trail on the west side of US 41 and a variable-width sidewalk on the east side of US 41; replacing existing underground drainage and utility structures, and installing new LED streetlights and landscaping. Other improvements include raised pedestrian refuge islands and a HAWK pedestrian signalization system. Use caution and watch for changes in the traffic pattern. Wright Construction, Inc. is the contractor. Expected completion is fall 2020.

  • The week of October 21, motorists should expect possible nighttime lane closures from 9 p.m. to 7 a.m. 

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, November 1. Use caution and expect possible delays.

Continue reading
  215 Hits
0 Comments
215 Hits
  0 Comments
Oct
04

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF OCTOBER 6, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is early 2020. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed through late fall. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, October 6 through Saturday, October 12. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, October 6 through Saturday, October 12. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. Motorists should expect right turn lane closures from Rye Road to westbound SR 64 from 9 a.m. to 4 p.m. daily through Friday, October 11 while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

SARASOTA COUNTY

US 41 Roundabouts at 10th Street and 14th Street, Sarasota: Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Traffic pattern shift to the west is expected starting Tuesday, October 8th. Work is expected Sunday, Monday, and possibly Tuesday night in preparation for the traffic pattern change. Expect lane closures and flaggers/law enforcement officers directing traffic at 10th Street and 14th Street.
  • South bound traffic will be shifted onto the newly constructed roadway. Pay close attention to the new pavement markings and signs, more importantly at the intersections.
  • Following the traffic switch, the project work zone will shift to the east side of US 41, in the current north bound lanes.
  • Paving is expected along US 41 from 10th Street to 14th Street. Be mindful of asphalt trucks entering and leaving the roadway. Expect vibration from rollers.
  • Roadway base work and asphalt paving is expected at the SW corner of 14th Street and SW corner of 10th Street. Expect vibration from rollers.
  • Light pole installation is expected at 10th and 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • The installation of temporary traffic devices and stripping will occur on new asphalt. No impacts to the current travel lanes are expected but use caution on southbound lanes as crews will be working close to the current southbound lanes.
  • The right turn lane on westbound 10th Street, east of US 41 is closed. The through lane now serves as a through and right turn lane.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, October 11. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Seaboard Avenue is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Wednesday, September 25.
  • Expect northbound and southbound nighttime lane closures for roadway maintenance Monday through Saturday on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. through Sunday, October 13.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, October 4. Use caution and expect possible delays.

Continue reading
  241 Hits
0 Comments
241 Hits
  0 Comments
Oct
04

Celebrate Sarasota “Bike to Work Day” event during Mobility Week

mobility-week-2019 Mobility Week 2019

Bartow, FL - The Florida Department of Transportation’s Commute Connector program has partnered with the City of Sarasota, Sarasota County and Sarasota-Manatee Metropolitan Planning Organization (MPO) to host a “Bike to Work Day” event.  The ride, which will take place before work in downtown Sarasota will take place on Friday, November 1, 2019 starting at 7:30 a.m.  The event is part of Mobility Week, an annual initiative from October 25 through November 1, 2019.  Mobility Week is a coordinated and concentrated celebration of activities to promote transportation choices and safety. 

Commuters that live or work in the greater Sarasota area are invited to grab their bike and helmets, pump up their tires and join us at Payne Park, 2010 Adams Lane, Sarasota, FL 34237.  Participants will enjoy a scenic loop through Sarasota’s vibrant downtown with colleagues, neighbors and friends.  Registration for the event opens at 7:30 a.m. in the amphitheater area of Payne Park. The guided group ride will begin at 8:00 a.m., and will end by 9:00 a.m. in the same place the ride started.  The 2.5-mile, slow-paced ride will be escorted by the Sarasota Police Department. 

During the event, an on-site transportation fair will allow residents and commuters to learn more about their commute options from the City of Sarasota, Sarasota County, Sarasota-Manatee MPO and Sarasota County Area Transit.  Coffee, water and donuts will be provided at the start of the ride courtesy of Kimley-Horn.  Helmets are strongly encouraged.  

To learn more and to register online, visit https://sarasotabiketoworkday2019.eventbrite.com.  Contact Commute Connector at 866-585-RIDE (4733) or This email address is being protected from spambots. You need JavaScript enabled to view it. with questions.

Continue reading
  228 Hits
0 Comments
228 Hits
  0 Comments
Sep
20

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF SEPTEMBER 22, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, September 22 through Saturday, September 28. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, September 22 through Saturday, September 28. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217):  Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer/early fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. Beginning Monday, September 23 through Friday, October 11, motorists should expect right turn lane closures from Rye Road to westbound SR 64 from 9 a.m. to 4 p.m. daily while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

SARASOTA COUNTY

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed at 10th and 14th Street.
  • Sidewalk is expected to be installed at 14th Street. Expect concrete trucks entering and exiting the travel lanes.
  • Roadway base work and asphalt paving is expected at the SW corner of 14th Street and SW corner of 10th Street. Expect vibration from rollers.
  • Work is expected along US 41 from 11th Street to 14th Street for watermain tie ins. 11th Street and 12th Street will remain closed at US 41. There will be temporary disruption in service for the a few residents/businesses along 13th Street. The City of Sarasota will notify and coordinate shutdowns with the impacted residents as needed. Expect backup alarms, excavators, pumps while work is being performed. 
  • Paving is expected along US 41 from 10th Street to 14th Street. Be mindful of asphalt trucks entering and leaving the roadway. Expect vibration from rollers.
  • Drainage work is expected at the boat ramp area, no disruption to boat ramp access is expected at this time.
  • Light pole installation is expected at 10th and 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • The installation of temporary traffic devices and stripping will occur on new asphalt. No impacts to the current travel lanes are expected but use caution on southbound lanes as crews will be working close to the current southbound lanes.
  • The right turn lane on westbound 10th Street, east of US 41 will be closed at the end of the week. Concrete barrier wall will be installed to close off the lane. The installation is expected to take half a day, during this time a semi-truck and equipment crossing in and out of 10th Street is expected. Be alert for flaggers while the barrier wall is being installed. The through lane will now serve as a through and right turn lane.
  • Traffic switch to Phase 2 is expected in 2 weeks. Both north bound and south bound lanes will be shifted to the west for the upcoming phase. The shift will occur at night. If traveling within the project between 7 p.m. and 6 a.m., be alert for lane closures, lane shifts, flaggers, and police officers directing motorists.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED streetlights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, September 27. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is late summer/early fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Seaboard Avenue is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Wednesday, September 25.
  • Expect northbound and southbound nighttime lane closures for roadway maintenance Monday through Saturday on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. through Sunday, October 6.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer/early fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, September 27. Use caution and expect possible delays.

Continue reading
  211 Hits
0 Comments
211 Hits
  0 Comments
Sep
13

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF SEPTEMBER 15, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, September 15 through Saturday, September 21. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, September 15 through Saturday, September 21. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 on-ramp to I-75 northbound will be closed during the overnight hours from     1 p.m. to 5 a.m. on Sunday, September 15th, weather permitting.  Weather make-up date is Monday, September 16th.
  • Motorists wishing to travel northbound on I-75 are advised to take I-75 southbound to Exit 224/University Parkway and return to the interstate northbound; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 301 (State Road 43) from 2nd Avenue to 51st Avenue: Construction project: Crews are resurfacing the roadway; improving drainage; installing guardrail and highway lighting, and improving the railroad crossing. Expect nighttime/overnight lane closures from 9 p.m. to 5:30 a.m. and possible daytime lane closures from 9 a.m. to 4 p.m. during construction. Superior Asphalt, Inc. is the contractor. Expected completion is summer 2020.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer/early fall 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. During the week of Monday, September 23 through Friday, September 27 motorists should expect right turn lane closures from Rye Road to westbound SR 64 from 9 a.m. to 4 p.m. daily while crews are working. IBT Construction is the contractor. Expected completion is late 2019/early 2020.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed at 10th and 14th Street.
  • Sidewalks are expected to be installed at 10th and 14th Street. Expect concrete trucks entering and exiting the travel lanes.
  • Roadway base work and asphalt paving is expected at the SW corner of 14th Street and SW corner of 10th Street. Expect vibration from rollers.
  • Work is expected along US 41 from 11th Street to 14th Street for watermain tie ins. 11th Street and 12th Street will remain closed at US 41. There will be temporary disruption in service for the a few residents/businesses along 13th Street. The City of Sarasota will notify and coordinate shutdowns with the impacted residents as needed. Expect backup alarms, excavators, pumps while work is being performed. 
  • Paving is expected along US 41 from 10th Street to 14th Street. Be mindful of asphalt trucks entering and leaving the roadway. Expect vibration from rollers.
  • Waterline and drainage work are expected at the boat ramp area, no disruption to boat ramp access is expected at this time.
  • Light pole installation and sidewalk installation expected at 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • Traffic switch to Phase 2 is expected in 2 weeks. Both north bound and south bound lanes will be shifted to the west for the upcoming phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, September 27. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is late summer/early fall 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Thursday, September 12.
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday,    September 16 through Sunday, October 6.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer/early fall 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, September 27. Use caution and expect possible delays.

Continue reading
  210 Hits
0 Comments
210 Hits
  0 Comments
Sep
05

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF SEPTEMBER 8, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, September 8 through Saturday, September 14. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, September 8 through Saturday, September 14. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 on-ramp to I-75 northbound will be closed during the overnight hours from 11 p.m. to 5 a.m. on Friday, September 13th, weather permitting.  Weather make-up date is Sunday, September 15th.
  • Motorists wishing to travel northbound on I-75 are advised to take I-75 southbound to Exit 224/University Parkway and return to the interstate northbound; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from  8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed at 10th and 14th Street.
  • Sidewalks are expected to be installed at 10th and 14th Street. Expect concrete trucks entering and exiting the travel lanes.
  • Roadway base work is expected at the SW and SE corner of 14th Street. Expect vibration from rollers.
  • Work is expected at along US 41 from 11th Street to 14th Street for watermain tie ins. There will be temporary disruption in service for the a few water services along      US 41, along 13th Street and 14th Street. Expect backup alarms, excavators, pumps while work is being performed. The City of Sarasota will notify and coordinate shutdowns with the impacted residents as needed.
  • Waterline and drainage work are expected at the boat ramp area, no disruption to boat ramp access is expected at this time.
  • Light pole installation and sidewalk installation expected at 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • Traffic switch to Phase 2 is expected in 3 to 4 weeks. Both north bound and south bound lanes will be shifted to the west for the upcoming phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, September 13. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, September 13. Use caution and expect possible delays.

Continue reading
  345 Hits
0 Comments
345 Hits
  0 Comments
Aug
22

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF AUGUST 25, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, August 25 through Thursday, August 29. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, August 25 through Thursday, August 29. Lane closures are not permitted during the Labor Day holiday beginning Friday, August 30 through Monday, September 2. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, signals and lighting, and working on the bridges over SR 70 and the Braden River.

  • SR 70 westbound will be closed underneath I-75 during the overnight hours from    11 p.m. to 5 a.m. on Monday, August 26th, weather permitting, while crews install interstate bridge concrete deck.  Beginning at 8 p.m. each evening, crews will close two lanes on SR 70 westbound, with the total closure beginning at 11 p.m.  Weather make-up date, if needed, is Tuesday, August 27th.
  • Motorists wishing to travel SR 70 westbound are advised take I-75 northbound to Exit 220/SR 64 and return to the interstate southbound and exit at Exit 217/SR 70; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Beginning Monday, August 5, and continuing for the next two weeks, there will be extended bridge openings between midnight and 4 a.m. while the contractor is working. The openings are expected to take up to 30 minutes each occurrence. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews Continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed at 10th and 14th Street.
  • Sidewalks are expected to be installed at 10th and 14th Street. Expect concrete trucks entering and exiting the travel lanes.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • Night work is expected at 10th and 11th Street for watermain tie ins in 2 weeks. This work is tentatively scheduled and is dependent on weather and local agency approvals. Expect backup alarms, excavators, pumps while work is being performed. Hours of activity is expected 6 p.m. to 6 a.m.
  • Light pole installation and sidewalk installation expected at 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only one lane going east and one lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, August 30. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings. Paving operations are expected to begin the evening of Sunday, August 25 and continue throughout the week.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from  7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Traffic is anticipated to switch back to Seaboard Avenue on Wednesday, August 28.  
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, August 25 through Friday, August 30.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 758 at the Siesta Key Drawbridge: Bridge maintenance project: Crews are working on the bridge. Expect nighttime/overnight intermittent lane closures from 9 p.m. each night to   5 a.m. each morning Monday, August 26 through Thursday, August 29. Use caution and expect possible delays.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, August 30. Use caution and expect possible delays.

Continue reading
  336 Hits
0 Comments
336 Hits
  0 Comments
Aug
15

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF AUGUST 18, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure; however, there will be intermittent flagging operations along the fishing pier access road in Manatee County for moving of equipment and materials. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, August 18 through Saturday, August 25. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, August 18 through Saturday, August 25. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, signals and lighting, and working on the bridges over SR 70 and the Braden River.

  • SR 70 eastbound will be closed underneath I-75 during the overnight hours from 11 p.m. to 5 a.m. on Tuesday, August 20th, weather permitting, while crews install interstate bridge concrete deck.  Beginning at 8 p.m. each evening, crews will close two lanes on SR 70 eastbound, with the total closure beginning at 11 p.m.  Weather make-up date, if needed, is Wednesday, August 21st.
  • Motorists wishing to travel SR 70 eastbound are advised take I-75 southbound to  Exit 213/University Parkway and return to the interstate northbound and exit at     Exit 217/SR 70; or, use local routes.
  • I-75 northbound and southbound off-ramps to SR 70 will be reduced to one lane each evening from 8 p.m. to 5 a.m.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at US 301: Maintenance project: Crews are making roadway repairs to the I-75 southbound on-ramps from US 301. Motorists should expect nighttime/overnight lane shifts and reduced lane widths from 11 p.m. to 5 a.m. Monday, August 19 while crews are working, weather permitting. Should weather delay work on Monday, work will occur on Tuesday, August 20 instead.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Beginning Monday, August 5, and continuing for the next two weeks, there will be extended bridge openings between midnight and 4 a.m. while the contractor is working. The openings are expected to take up to 30 minutes each occurrence. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed along US 41 on the west side and on 14th Street.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • Night work is expected at 10th and 11th street for watermain tie ins in 2 weeks. This work is tentatively scheduled and is dependent on weather and local agency approvals. Expect backup alarms, excavators, pumps while work is being performed. Hours of activity is expected 6 p.m. to 6 a.m.
  • Light pole installation and sidewalk installation expected at 14th Street. Expect concrete trucks entering and exiting the construction zones.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only one lane going east and one lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, August 23. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings. Paving operations are expected to begin the evening of Sunday, August 18 and continue throughout the week.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, August 18 through Friday, August 23.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, August 30. Use caution and expect possible delays.

Continue reading
  281 Hits
0 Comments
281 Hits
  0 Comments
Aug
08

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF AUGUST 11, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  There will be a short duration shoulder closure on I-275 northbound at the end of the on-ramp from the Manatee County rest area.  This is expected to be in place for one to two hours only, at the beginning of week of July 21 and again during the week of July 28 and will take place off interstate. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, August 11 through Saturday, August 17. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, August 11 through Saturday, August 17. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating interchange and SR 70 stormwater ponds and drainage, signals and lighting, and working on the bridges over SR 70 and the Braden River.

  • SR 70 eastbound will be closed underneath I-75 during the overnight hours from     11 p.m. to 5 a.m. on Thursday, August 15th, weather permitting, while crews install interstate bridge concrete deck.  Beginning at 8 p.m. each evening, crews will close two lanes on SR 70 eastbound, with the total closure beginning at 11 p.m.  Weather make-up date, if needed, is Friday, August 16th.
  • Motorists wishing to travel SR 70 eastbound are advised take I-75 southbound to  Exit 213/University Parkway and return to the interstate northbound and exit at     Exit 217/SR 70; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Beginning Monday, August 5, and continuing for the next two weeks, there will be extended bridge openings between midnight and 4 a.m. while the contractor is working. The openings are expected to take up to 30 minutes each occurrence. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue is tentatively scheduled to open to traffic by Sunday, August 4. Nighttime/overnight lane closures from 7 p.m. to  6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed along US41 on the west side and on 14th Street.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • Night work is expected at 10th and 11th Street for watermain tie-ins. This work is tentatively scheduled and is dependent on weather and local agency approvals. Expect backup alarms, excavators, pumps while work is being performed. Hours of activity are expected 6 p.m. to 6 a.m.
  • Light pole installation and sidewalk installation expected at 14th Street. Expect concrete trucks entering and exiting the construction zone.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only one lane going east and one lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, August 16. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings. Paving operations are expected to begin Sunday, August 11 and continue throughout the week.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Traffic is anticipated to switch back to Seaboard Avenue on Wednesday, August 21.  
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, August 4 through Thursday, August 15.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Wednesday, August 14.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, August 30. Use caution and expect possible delays.

 

Continue reading
  262 Hits
0 Comments
262 Hits
  0 Comments
Aug
02

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF AUGUST 4, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  There will be a short duration shoulder closure on I-275 northbound at the end of the on-ramp from the Manatee County rest area.  This is expected to be in place for one to two hours only, at the beginning of week of July 21 and again during the week of July 28 and will take place off interstate. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, August 4 through Saturday, August 10. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, August 4 through Saturday, August 10. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, excavating stormwater ponds, drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from  8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Beginning Monday, August 5, and continuing for the next two weeks, there will be extended bridge openings between midnight and 4 a.m. while the contractor is working. The openings are expected to take up to 30 minutes each occurrence. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. On Tuesday, August 6, the traffic signal SR 64 and Rye Road will be temporarily deactivated between the hours of 9 a.m. and 4 p.m. During this time, law enforcement will direct traffic through the intersection. Please use caution and expect possible delays. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue is tentatively scheduled to open to traffic by Sunday, August 4. Nighttime/overnight lane closures from 7 p.m. to  6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301 between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to changes in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Brick pavers are expected to be installed along US 41 on the west side and on 14th Street.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Light pole installation and sidewalk installation expected at14th Street.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, August 9. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Traffic is anticipated to switch back to Seaboard Avenue on Tuesday, August 13.  
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, August 4 through Thursday, August 15.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Wednesday, August 14.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, August 30. Use caution and expect possible delays.

Continue reading
  133 Hits
0 Comments
133 Hits
  0 Comments
Jul
25

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF JULY 28, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  There will be a short duration shoulder closure on I-275 northbound at the end of the on-ramp from the Manatee County rest area.  This is expected to be in place for one to two hours only, at the beginning of week of July 21 and again during the week of July 28 and will take place off interstate. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, July 28 through Saturday, August 3. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, July 28 through Saturday, August 3. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor. 

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.

Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west. 

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to changes in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • 10th Street is scheduled to be closed starting Monday, July 22nd for installation of drainage pipe. Motorists can use Boulevard  of the Arts as alternate route. The closure is expected to last until Wednesday, July 24th.
  • Lane closures are expected on US 41 just north and north of 10th Street for installation of drainage pipe across US 41 south of 10th Street. Closures are expected during daytime hours from 9am to 4pm. Expect equipment and construction personnel working close to the travel lanes.
  • Brick pavers are expected to be installed along US 41 on the west side.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, August 2. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m. 

The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019.  

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, July 21 through Sunday, August 4.

Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Wednesday, July 31.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.
 
SR 72 (Clark Road) at Bee Ridge Road Extension/Lorraine Road: Maintenance permit project: Crews are constructing a right turn-lane. Expect intermittent lane closures and flagging operations from 9 p.m. each night to 5 a.m. each morning through Friday, August 30. Use caution and expect possible delays.
 
I-75 mile marker 196 before Laurel Road: Maintenance project: Crews will be making asphalt repairs to the left lane on southbound I-75 just before the Laurel Road. Motorists should expect lane closures at the left and center lanes approaching Laurel Road from 10 p.m. on Wednesday, July 31 to 5 a.m. on Thursday, August 1, weather permitting. Use caution and expect possible delays.

I-75 mile marker 204 near Exit 205 before Clark Road: Maintenance project: Crews will be making asphalt repairs to the right lane on southbound I-75 just before Clark Road.  Motorists should expect lane closures at the right and middle lanes approaching exit 205 from 10 p.m. on Tuesday, July 30 from 10 p.m. to 5 a.m. on Wednesday, July 31, weather permitting. Use caution and expect possible delays.

Continue reading
  276 Hits
0 Comments
276 Hits
  0 Comments
Jul
22

Public Hearing Notice: US 41 at Dr. MLK Jr. Way and Myrtle Street Intersection Improvements PD&E Study, Sarasota County

Aug-15-PDE-Hearing Project and Hearing Location Map

The Florida Department of Transportation (FDOT), District One, is holding a public hearing for the preferred improvements to, and between, the intersections of US 41 at Dr. Martin Luther King (MLK) Jr. Way and US 41 at Myrtle Street in the City of Sarasota. We invite you to attend the hearing on Thursday, August 15, 2019 at the Robert L. Taylor Community Complex building at 1845 34th Street, Sarasota, Florida 34234. A project location map is included below for your reference.

The hearing will begin with an open house at 5 p.m. and follow with a formal presentation and public comment period at 6 p.m. People attending the hearing may review project displays and aerial photographs, and speak one-on-one with project team members about proposed improvements to the study corridor. 

This hearing is being held to allow interested persons an opportunity to be informed and provide comments concerning the location; conceptual design alternatives; and the social, economic, and environmental effects of the proposed improvements to US 41. The purpose of this project is to enhance safety, non-motorized connectivity, and access, as well as vehicular traffic flow and operations, between residences and schools of the northern Downtown Sarasota area and the Bayfront area.. The proposed improvements are similar to improvements that have been identified at other intersections along US 41 that are intended to improve traffic flow and enhance safety. The No-Build Alternative, which assumes that no improvements will be made along US 41, is also an option and will remain a viable alternative throughout the PD&E study.

Additional information may be obtained by contacting the FDOT Project Manager, David C. Turley, PE at 863.519.2255, by e-mail to This email address is being protected from spambots. You need JavaScript enabled to view it. or by writing to Florida Department of Transportation, Attn: David C. Turley, 801 North Broadway Avenue, Bartow, Florida 33830. Draft project reports and conceptual plans will be available for public review 21 days prior to the hearing at North Sarasota Public Library at 2801 Newton Blvd., Sarasota, Florida 34234  (Please call the library at (941) 861-1360 for hours of operation) and at the Florida Department of Transportation Office in Bartow, Florida (Monday through Friday, 8 a.m. to 5 p.m.).

FDOT is sending notices about the hearing to all property owners located within 300 feet of the project limits, and to interested parties. FDOT welcomes and appreciates the community’s participation in the project. The hearing gives interested parties an opportunity to express their views about the proposed improvements.

The hearing is developed in compliance with Title VI of the Civil Rights Act of 1964 and related statutes. FDOT solicits public participation without regard to race, color, national origin, age, sex, religion, disability, or family status. Persons who require special accommodations under the Americans with Disabilities Act (ADA) or persons who require translation services (free of charge) should contact Mr. David C. Turley, FDOT Project Manager, at (863) 519‐2255 or by e‐mail at This email address is being protected from spambots. You need JavaScript enabled to view it. at least seven (7) days prior to the hearing. If you are hearing or speech impaired, please contact the agency using the Florida Relay Services, 1.800.955.8771 (TDD) or 1.800.955.8770 (Voice). Additional information can be found on the project website at www.swflroads.com/us41/atmyrtlestreet&mlkjrway.

The environmental review, consultation, and other actions required by applicable federal environmental laws for this project are being, or have been, carried-out by FDOT pursuant to 23 U.S.C. §327 and a Memorandum of Understanding dated December 14, 2016, and executed by FHWA and FDOT.

Continue reading
  347 Hits
0 Comments
347 Hits
  0 Comments
Jul
12

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF JULY 14, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, July 14 through Saturday, July 20. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, July 14 through Saturday, July 20. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 will have two lanes closed in each direction beginning at 8 p.m. to 5 a.m. each evening starting Sunday, July 14th through Friday, July 19th.  I-75 northbound and southbound off-ramps to SR 70 will be reduced to one lane each evening from 8 p.m. to 5 a.m. 
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Contractor will be connecting new waterlines at 9th Street and 10th Street on July 10th.
  • 9th Street is scheduled to be closed for through traffic starting July 8th in preparation for the waterline tie in and expected to stay closed until Wednesday (July 17th)
  • Contractor is scheduled to work nights south of 10th Street on US 41 for the installation of stormwater pipe across US 41. Nighttime lane closures are expected on the SB lanes starting 7/15/19 to 7/17/19 between the hours of 8pm to 6am. Expect noise from equipment used for excavation, backup alarms, pumps etc. Use caution in the area and watch for trucks, equipment and construction personnel close to the travel lanes
  • 10th Street is scheduled to be closed end of next week for installation of drainage pipe. Motorists can use Boulevard of the Arts as alternate route. The closure is expected to last until Friday, July 19th.
  • Brick pavers are expected to be installed along US 41 on the west side.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, July 21 through Friday July 26.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Tuesday, July 23.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  250 Hits
0 Comments
250 Hits
  0 Comments
Jul
08

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF July 7, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, July 7 through Saturday, July 13. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, July 7 through Saturday, July 13. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 westbound will be closed during the overnight hours from 11 p.m. to 5 a.m. on Wednesday, July 10th and Thursday, July 11th underneath I-75 while crews install interstate bridge beams; weather permitting.  Beginning at 8 p.m. each evening, crews will close two lanes on SR 70 westbound, with the total closure beginning at 11 p.m.  SR 70 eastbound will have two lanes closed beginning at 8 p.m. each evening but will remain open.  I-75 northbound and southbound off-ramps to SR 70 will be reduced to one lane each evening from 8 p.m. to 5 a.m. 
  • Motorists wishing to travel SR 70 westbound are advised take I-75 northbound to Exit 220/SR 64 and return to the interstate southbound and exit at Exit 217/SR 70; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to changes in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Contractor will be connecting new waterlines at 9th Street and 10th Street on July 10th. There will be waterline shut down for the night of July 10th.
  • Waterline tie in at 9th Street is expected the night of July 10th. Expect light construction equipment and noise from backup alarms, power tools and pumps. Work is expected from 8pm to 6am.
  • 9th Street is scheduled to be closed for through traffic starting July 8th in preparation for the waterline tie in.
  • 10th Street is scheduled to be closed end of next week for 2 days for installation of drainage pipe. Motorists can use Boulevard of the Arts as alternate route.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  269 Hits
0 Comments
269 Hits
  0 Comments
Jun
27

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF JUNE 30, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, June 30 through Saturday, July 6, excluding Thursday July 4. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, June 30 through Saturday, July 6, excluding Thursday, July 4. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota: Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Construction operations will be shutdown starting June 28th thru July 7th to accommodate the Sarasota Powerboat Grand Prix boat races. Construction activities will resume on Monday July 8th.
  • Contractor personnel are expected to be onsite periodically for monitoring the equipment and traffic control devices during the shutdown period.
  • Sarasota Powerboat Grand Prix organizers are expected to shutdown 10th Street on the west side for their events, end of next week.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday,      July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

 

Continue reading
  218 Hits
0 Comments
218 Hits
  0 Comments
Jun
20

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF JUNE 23, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 24 through Friday, June 28. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 24 through Friday, June 28. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Beginning Friday, June 21, crews will be making drainage improvements on US 301 between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Paving is scheduled along US41 on the west side and at 10th Street, and the intersection of 14th Street. Work will occur during the night throughout the week. Lane closures are expected during the operation, with trucks and rollers. Expect noise from backup alarms and vibrations from compaction.
  • Testing and flushing of waterline at the SW corner of Imperial Drive scheduled. This activity is expected to last 1 week. There will be noise from excavators and pumps. Work currently is expected during daytime only.
  • Installation of brick pavers is expected along the west side of US 41.
  • Installation of traffic separators on the western edge of the current travel lanes is expected. Use caution as crews work close to the active travel lanes.
  • Installation of drainage structures and road base work at the SW corner of 10th Street and along 10th Street on the south side.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, June 28. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Via Veneto and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, June 24 through Friday, June 28.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  273 Hits
0 Comments
273 Hits
  0 Comments
Jun
13

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF JUNE 16, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 17 through Friday, June 21. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 17 through Friday, June 21. Use caution and watch for changes in the traffic pattern. Expected completion is late summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • During the overnight hours between Monday, June 17th and the morning of Tuesday, June 18th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be shifted about 1-mile to the south.  The new exit ramp begins immediately north of Linger Lodge Road overpass.  Signs will be present to inform motorists. If weather conditions prohibit the ramp work, the work will be shifted to Tuesday night into the morning of Wednesday, June 19th.
  • During the overnight hours between Monday, June 17th and the morning of Tuesday, June 18th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be closed while crews work on opening the new ramp which will be shifted about 1-mile to the south.  Motorists travelling northbound I-75 wishing to exit at Exit 217/SR 70 should either exit at Exit 213/University Parkway and use local routes; or, continue to Exit 220/SR 64 returning to I-75 and exit at Exit 217/SR 70.  If weather conditions prohibit the ramp work, the work will be shifted to Tuesday night into the morning of Wednesday, June 19th.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 70 at Seminole Gulf Railways Railroad crossing in Oneco: Construction project: Crews are upgrading the tracks and roadway at the rail crossing.  This week, crews will be performing work on the railroad tracks and crossing sub-structure. 

  • The improvements require a total closure of SR 70; therefore, SR 70 will be closed to through traffic at the rail crossing from Saturday, June 8th through Friday, June 21st. 
  • East of the rail crossing, SR 70 will be open to local traffic only from US 301 to 18th St Boulevard E.
  • West of the rail crossing, SR 70 will be open to local traffic only from US 41/14th Street W to 17th Street Court E. 
  • FDOT urge motorists to follow the posted detour or identify alternate routes. The posted detour for SR 70 westbound is SR 70 to US 301 to 63rd Avenue E to 14th Street W to SR 70.  For SR 70 eastbound traffic, follow SR 70 to 14th Street W to 63rd Avenue E to US 301 to SR 70 eastbound. 

The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is June 21, 2019; weather permitting.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue will close to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Beginning the week of Monday, June 17, crews will be making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Paving is scheduled along US41 on the west side and at 10th Street, and the intersection of 14th Street. Work will occur during the night throughout the week. Lane closures are expected during the operation, with trucks and rollers. Expect noise from backup alarms and vibrations from compaction.
  • Installation of waterline at the SW corner of Imperial Drive continues. This activity is expected to last 1 week. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during daytime only.
  • Installation of drainage structures and road base work at the SW corner of 10th Street and along 10th Street on the south side.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Work on the permanent driveway for Centennial Park boat ramp exit off US 41. Driveway to the north is accessible.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday,     June 21. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Via Veneto and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, June 17 through Friday, June 21.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  280 Hits
0 Comments
280 Hits
  0 Comments
Jun
10

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF June 9, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 10 through Friday, June 14. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 10 through Friday, June 14. Use caution and watch for changes in the traffic pattern. Expected completion is late summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • During the overnight hours between Friday, June 14th and the morning of Saturday, June 15th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be shifted about one mile to the south.  The new exit ramp begins immediately north of Linger Lodge Road overpass.  Signs will be present to inform motorists.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 70 at Seminole Gulf Railways Railroad crossing in Oneco: Construction project: Crews are upgrading the tracks and roadway at the rail crossing.  This week, crews will be performing work on the railroad tracks and crossing sub-structure. 

  • The improvements require a total closure of SR 70; therefore, SR 70 will be closed to through traffic at the rail crossing from Saturday, June 8th through Friday, June 21st. 
  • East of the rail crossing, SR 70 will be open to local traffic only from US 301 to 18th St Boulevard E.
  • West of the rail crossing, SR 70 will be open to local traffic only from US 41/14th Street W to 17th Street Court E. 
  • FDOT urge motorists to follow the posted detour or identify alternate routes. The posted detour for SR 70 westbound is SR 70 to US 301 to 63rd Avenue E to 14th Street W to SR 70.  For SR 70 eastbound traffic, follow SR 70 to 14th Street W to 63rd Avenue E to US 301 to SR 70 eastbound. 

The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is June 21, 2019; weather permitting.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue will close to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Installation of waterline under US 41 by boring under the road at the south east and south west corners. This activity is expected to last 1 week. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during daytime only.
  • Installation of drainage structures and road base work at the SW corner of 10th Street.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from 9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Work on the permanent driveway for Centennial Park boat ramp exit off US 41. Driveway to the north is accessible.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, June 14. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Seaboard Avenue is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  260 Hits
0 Comments
260 Hits
  0 Comments
We are committed to ensuring that this website is accessible to everyone under WAI-AA and US Section 508, making use of World Wide Web Consortium (W3C) standards. If you have any questions or suggestions regarding the accessibility of this site, please use our contact form.


Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public-records request, do not send electronic mail to this entity. Instead, contact this office by phone at 941-359-5772. Please note that our phone system can capture a voicemail as a recording, which if emailed may also be subject to a public-records request.