Jul
12

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF JULY 14, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, July 14 through Saturday, July 20. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, July 14 through Saturday, July 20. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 will have two lanes closed in each direction beginning at 8 p.m. to 5 a.m. each evening starting Sunday, July 14th through Friday, July 19th.  I-75 northbound and southbound off-ramps to SR 70 will be reduced to one lane each evening from 8 p.m. to 5 a.m. 
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Contractor will be connecting new waterlines at 9th Street and 10th Street on July 10th.
  • 9th Street is scheduled to be closed for through traffic starting July 8th in preparation for the waterline tie in and expected to stay closed until Wednesday (July 17th)
  • Contractor is scheduled to work nights south of 10th Street on US 41 for the installation of stormwater pipe across US 41. Nighttime lane closures are expected on the SB lanes starting 7/15/19 to 7/17/19 between the hours of 8pm to 6am. Expect noise from equipment used for excavation, backup alarms, pumps etc. Use caution in the area and watch for trucks, equipment and construction personnel close to the travel lanes
  • 10th Street is scheduled to be closed end of next week for installation of drainage pipe. Motorists can use Boulevard of the Arts as alternate route. The closure is expected to last until Friday, July 19th.
  • Brick pavers are expected to be installed along US 41 on the west side.
  • Roadway base work is expected at the SW and SE corner of 14th Street.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Sunday, July 21 through Friday July 26.
  • Expect a new change in traffic pattern for northbound and southbound traffic on US 41 between Center Road and Gulf Coast Boulevard beginning Tuesday, July 23.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  75 Hits
0 Comments
75 Hits
  0 Comments
Jul
08

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF July 7, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing pier will remain open during the closure. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, July 7 through Saturday, July 13. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, July 7 through Saturday, July 13. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • SR 70 westbound will be closed during the overnight hours from 11 p.m. to 5 a.m. on Wednesday, July 10th and Thursday, July 11th underneath I-75 while crews install interstate bridge beams; weather permitting.  Beginning at 8 p.m. each evening, crews will close two lanes on SR 70 westbound, with the total closure beginning at 11 p.m.  SR 70 eastbound will have two lanes closed beginning at 8 p.m. each evening but will remain open.  I-75 northbound and southbound off-ramps to SR 70 will be reduced to one lane each evening from 8 p.m. to 5 a.m. 
  • Motorists wishing to travel SR 70 westbound are advised take I-75 northbound to Exit 220/SR 64 and return to the interstate southbound and exit at Exit 217/SR 70; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to changes in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Contractor will be connecting new waterlines at 9th Street and 10th Street on July 10th. There will be waterline shut down for the night of July 10th.
  • Waterline tie in at 9th Street is expected the night of July 10th. Expect light construction equipment and noise from backup alarms, power tools and pumps. Work is expected from 8pm to 6am.
  • 9th Street is scheduled to be closed for through traffic starting July 8th in preparation for the waterline tie in.
  • 10th Street is scheduled to be closed end of next week for 2 days for installation of drainage pipe. Motorists can use Boulevard of the Arts as alternate route.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  113 Hits
0 Comments
113 Hits
  0 Comments
Jun
27

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF JUNE 30, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Sunday, June 30 through Saturday, July 6, excluding Thursday July 4. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Sunday, June 30 through Saturday, July 6, excluding Thursday, July 4. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Crews are making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota: Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Construction operations will be shutdown starting June 28th thru July 7th to accommodate the Sarasota Powerboat Grand Prix boat races. Construction activities will resume on Monday July 8th.
  • Contractor personnel are expected to be onsite periodically for monitoring the equipment and traffic control devices during the shutdown period.
  • Sarasota Powerboat Grand Prix organizers are expected to shutdown 10th Street on the west side for their events, end of next week.
  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday,      July 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

 

Continue reading
  79 Hits
0 Comments
79 Hits
  0 Comments
Jun
20

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF JUNE 23, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain through the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 24 through Friday, June 28. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 24 through Friday, June 28. Use caution and watch for changes in the traffic pattern. Expected completion is fall 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue closed to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Beginning Friday, June 21, crews will be making drainage improvements on US 301 between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Paving is scheduled along US41 on the west side and at 10th Street, and the intersection of 14th Street. Work will occur during the night throughout the week. Lane closures are expected during the operation, with trucks and rollers. Expect noise from backup alarms and vibrations from compaction.
  • Testing and flushing of waterline at the SW corner of Imperial Drive scheduled. This activity is expected to last 1 week. There will be noise from excavators and pumps. Work currently is expected during daytime only.
  • Installation of brick pavers is expected along the west side of US 41.
  • Installation of traffic separators on the western edge of the current travel lanes is expected. Use caution as crews work close to the active travel lanes.
  • Installation of drainage structures and road base work at the SW corner of 10th Street and along 10th Street on the south side.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, June 28. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Via Veneto and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, June 24 through Friday, June 28.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  101 Hits
0 Comments
101 Hits
  0 Comments
Jun
13

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF JUNE 16, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

Various locations along SR 684 and US 301: Construction project: Crews are installing new highway lighting at various locations along SR 684 from Gulf Drive to 9th Street W and on US 301 from Tallevast Road to 9th Street E. Expect nighttime/overnight lane closures from 10:30 p.m. to 6 a.m. Expected completion is fall 2019. PowerCore, Inc. is the contractor.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 17 through Friday, June 21. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 17 through Friday, June 21. Use caution and watch for changes in the traffic pattern. Expected completion is late summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • During the overnight hours between Monday, June 17th and the morning of Tuesday, June 18th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be shifted about 1-mile to the south.  The new exit ramp begins immediately north of Linger Lodge Road overpass.  Signs will be present to inform motorists. If weather conditions prohibit the ramp work, the work will be shifted to Tuesday night into the morning of Wednesday, June 19th.
  • During the overnight hours between Monday, June 17th and the morning of Tuesday, June 18th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be closed while crews work on opening the new ramp which will be shifted about 1-mile to the south.  Motorists travelling northbound I-75 wishing to exit at Exit 217/SR 70 should either exit at Exit 213/University Parkway and use local routes; or, continue to Exit 220/SR 64 returning to I-75 and exit at Exit 217/SR 70.  If weather conditions prohibit the ramp work, the work will be shifted to Tuesday night into the morning of Wednesday, June 19th.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 70 at Seminole Gulf Railways Railroad crossing in Oneco: Construction project: Crews are upgrading the tracks and roadway at the rail crossing.  This week, crews will be performing work on the railroad tracks and crossing sub-structure. 

  • The improvements require a total closure of SR 70; therefore, SR 70 will be closed to through traffic at the rail crossing from Saturday, June 8th through Friday, June 21st. 
  • East of the rail crossing, SR 70 will be open to local traffic only from US 301 to 18th St Boulevard E.
  • West of the rail crossing, SR 70 will be open to local traffic only from US 41/14th Street W to 17th Street Court E. 
  • FDOT urge motorists to follow the posted detour or identify alternate routes. The posted detour for SR 70 westbound is SR 70 to US 301 to 63rd Avenue E to 14th Street W to SR 70.  For SR 70 eastbound traffic, follow SR 70 to 14th Street W to 63rd Avenue E to US 301 to SR 70 eastbound. 

The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is June 21, 2019; weather permitting.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue will close to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Beginning the week of Monday, June 17, crews will be making drainage improvements on US 301between Ringling Boulevard and Main Street. During this time, the northbound right lane will be closed. The northbound and southbound turn lanes will become through lanes for traffic. Northbound and southbound left turns from US 301 to Ringling Boulevard and to Main Street are prohibited. Motorists should use caution and pay close attention to chnages in traffic patterns. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Paving is scheduled along US41 on the west side and at 10th Street, and the intersection of 14th Street. Work will occur during the night throughout the week. Lane closures are expected during the operation, with trucks and rollers. Expect noise from backup alarms and vibrations from compaction.
  • Installation of waterline at the SW corner of Imperial Drive continues. This activity is expected to last 1 week. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during daytime only.
  • Installation of drainage structures and road base work at the SW corner of 10th Street and along 10th Street on the south side.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Work on the permanent driveway for Centennial Park boat ramp exit off US 41. Driveway to the north is accessible.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday,     June 21. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Beginning Tuesday, May 28 at 7 a.m., Seaboard Avenue will be closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days.
  • Expect northbound and southbound nighttime lane closures on US 41 between Via Veneto and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, June 17 through Friday, June 21.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  114 Hits
0 Comments
114 Hits
  0 Comments
Jun
10

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF June 9, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, June 10 through Friday, June 14. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, June 10 through Friday, June 14. Use caution and watch for changes in the traffic pattern. Expected completion is late summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, SR 70 drainage and curbs, installing signage, and working on the bridge the Braden River.

  • During the overnight hours between Friday, June 14th and the morning of Saturday, June 15th, the I-75 northbound off-ramp to SR 70 (Exit 217) will be shifted about one mile to the south.  The new exit ramp begins immediately north of Linger Lodge Road overpass.  Signs will be present to inform motorists.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789 at the Longboat Key Pass Bridge: Construction project: Crews are making structural, electrical and mechanical repairs on the bridge. Expect nighttime/overnight lane closures from 9 p.m. to 6 a.m. Sidewalk closures are also expected during construction. Southern Road & Bridge, LLC is the contractor. Expected completion is late summer 2019.

SR 70 at Seminole Gulf Railways Railroad crossing in Oneco: Construction project: Crews are upgrading the tracks and roadway at the rail crossing.  This week, crews will be performing work on the railroad tracks and crossing sub-structure. 

  • The improvements require a total closure of SR 70; therefore, SR 70 will be closed to through traffic at the rail crossing from Saturday, June 8th through Friday, June 21st. 
  • East of the rail crossing, SR 70 will be open to local traffic only from US 301 to 18th St Boulevard E.
  • West of the rail crossing, SR 70 will be open to local traffic only from US 41/14th Street W to 17th Street Court E. 
  • FDOT urge motorists to follow the posted detour or identify alternate routes. The posted detour for SR 70 westbound is SR 70 to US 301 to 63rd Avenue E to 14th Street W to SR 70.  For SR 70 eastbound traffic, follow SR 70 to 14th Street W to 63rd Avenue E to US 301 to SR 70 eastbound. 

The contractor is Ajax Paving Industries of Florida, LLC. Expected completion is June 21, 2019; weather permitting.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue will close to traffic overnight Thursday, June 13/early Friday, June 14 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to westbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue west.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east until the road closure at 6th Avenue Drive W. Otherwise, motorists will continue south on US 41 and exit at 10th Street W to continue eastbound as normal.  
  • Traffic eastbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street. Make a right-turn onto 10th Street to continue west.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Installation of waterline under US 41 by boring under the road at the south east and south west corners. This activity is expected to last 1 week. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during daytime only.
  • Installation of drainage structures and road base work at the SW corner of 10th Street.
  • A new traffic pattern on west side of 10th Street is implemented. Travel lanes have been slightly shifted north. There will be only 1 lane going east and 1 lane going west during the temporary phase.
  • New boat ramp driveway is open. Use caution as the wider driveway is intended for both entering and exiting traffic
  • Temporary single lane closures may occur between 9th Street and 15th Street from 9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Work on the permanent driveway for Centennial Park boat ramp exit off US 41. Driveway to the north is accessible.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, June 14. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Seaboard Avenue is closed to thru traffic while workers complete drainage improvements. Motorists should use Spur Street as a detour route. Seaboard Avenue is anticipated be closed for a total of 54 days. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  115 Hits
0 Comments
115 Hits
  0 Comments
May
21

Full Traffic Signal to be Installed at U.S. 301/CR 675 Intersection in Parrish

parrish Photo courtesy of Bradenton Herald

Joint effort by FDOT and Manatee County to continue to improve safety

Bartow, FL---The Florida Department of Transportation, in coordination with Manatee County, is planning to install a full four-way traffic signal at the intersection of U.S. 301 and CR 675 in the Village of Parrish.

After extensive community involvement and exploring a variety of options, FDOT has determined the best solution to provide a long-term safety and operational benefit for both residents and visitors who travel through the intersection.

In order to facilitate the operation of a traditional traffic signal, Manatee County will upgrade 69th Street from a narrow local road to a wider road that can accommodate the two-way traffic entering and exiting the US 301/CR 675 intersection.

“We are glad to partner with Manatee County to develop a plan that will meet the needs of the community with appropriate traffic control at the intersection, and the necessary roadway improvements,” said FDOT District 1 Secretary L.K. Nandam. 

In addition to widening 69th Street, the county plans to upgrade additional roads in the vicinity of the US 301/CR 675 intersection.

FDOT is working towards finalizing a start date for the installation of the new signal. Once construction begins, motorists may encounter occasional closures, detours and possible delays.  Motorists are urged to obey posted speed limits, pay attention to directional signs and allow for extra travel time.

Continue reading
  169 Hits
0 Comments
169 Hits
  0 Comments
May
16

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF MAY 19, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure; however, there will be periodic short intermittent flagging operations along the fishing pier access road on the Manatee side. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, May 20 through Friday, May 24. Expect nighttime/overnight lane closures on I-75 northbound and I-75 southbound between Moccasin Wallow Road and just south of the I-275 interchange from 9 p.m. each night to 6 a.m. each morning Monday, May 20 through Friday, May 24. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, utility installations, and working on the bridge the Braden River.

  • On Monday, May 20th through Friday, May 24th, crews will be working on the SR 70 at Ranch Lake Boulevard/River Club shopping center entrance intersection; weather permitting. The entrance will be open; however, lanes will be narrowed to allow for the work. Motorists should expect possible congestion.  Motorists may also access the plaza by continuing on SR 70 eastbound, then turning right onto Ranch Lake Boulevard/Ranch Lake Plaza entrance, then turning right to continue to Ranch Lake Boulevard/River Club.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SR 43 (10th Street) from 6th Avenue Drive W to 2nd Avenue: Construction project: Crews are making improvements to two railroad crossings, improving drainage, constructing sidewalk, and constructing turn lanes on State Road 43 (10th Street). State Road 43 (10th Street) between 6th Avenue Drive W and 2nd Avenue will close to traffic overnight Thursday, May 30/early Friday, May 31 and remain closed for approximately 70 days while crews are working.

  • Traffic northbound on US 41 to eastbound SR 43 (10th Street) will make a left-turn onto 7th Street W and continue to Business US 41 (8th Avenue W). Make a right-turn onto Business US 41 (8th Avenue W) and then make a left-turn on SR 43 (10th Street) to continue east.
  • Traffic southbound on US 41 to eastbound SR 43 (10th Street) will make a right-turn onto 17th Street W and continue to Business US 41 (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and then make right-turn onto SR 43 (10th Street) to continue east.
  • Traffic westbound on 10th Street will make a left-turn onto Business US 41 (8th Avenue W) and continue to 17th Street W. Make a right-turn onto 17th Street W and continue to US 41. Make a right-turn onto southbound US 41 and exit at SR 43 (10th Street) to continue west.
  • Traffic eastbound on 10th Street will merge onto US 41 northbound and continue to 17th Street W. Make a left-turn onto 17th Street W and continue to Business US 41       (8th Avenue W). Make a left-turn onto Business US 41 (8th Avenue W) and continue to 10th Street and make a right-turn to continue east.

Nighttime/overnight lane closures from 7 p.m. to 6 a.m. will occur throughout construction while crews are working. Expected completion is fall 2019. Preferred Materials, Inc., is the contractor.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from 8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Installation of waterline under US 41 by boring under the road at the south east and south west corners. This activity is expected to last 3 weeks. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during daytime only.
  • Installation of drainage structures at the SW corner of 10th Street is expected on Saturday, daytime.
  • Work is expected Sunday night (5/19/19) at 10th Street. Crews are expected to work on shifting traffic lights for 10th Street east bound. Expect heavy equipment, bucket trucks and pavement marking trucks. Work is expected from 6 p.m. to 6 a.m.
  • A new traffic pattern on west side of 10th Street is expected starting Monday night. Travel lanes will be slightly shifted north. The new pattern will be well marked and signed.
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Pedestrian crosswalks and stop bar on the south bound lanes at 14th Street are marked. For the safety of pedestrians, motorists are urged to stop at the designated stop bar.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • East bound right turn lane at 10th Street will be closed until underground utilities complete in the area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, May 31. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and James Street from 7 p.m. to 6 a.m. beginning Sunday, May 19 through Thursday, May 23.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

 

Continue reading
  142 Hits
0 Comments
142 Hits
  0 Comments
May
10

Traffic Watch for Manatee and Sarasota Counties

My-Post-1 Traffic Watch for Manatee and Sarasota Counties

FOR WEEK OF MAY 12, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, May 13 through Friday, May 17. Expect nighttime/overnight lane closures on the I-75 northbound ramp to I-275 northbound from 9 p.m. each night to 6 a.m. each morning Monday, May 13 through Friday, May 17. Expect nighttime/overnight lane closures on I-275 northbound and I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, May 13 through Friday, May 17. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, utility installations, and working on the bridge the Braden River.

  • On Monday, May 13th through Friday, May 17th, crews will be working on the intersection of SR 70 and Lena Road, weather permitting. The SR 70 eastbound turn lane to Lena Road will be CLOSED FROM 7 a.m. TO 7 p.m. during the work.  Lena Road will be open; however, lanes will be narrowed to allow for the work. Motorists should expect possible congestion.  Motorists may access Lena Road by continuing on SR 70 eastbound, then turning left onto 87th Street E, and turning left onto 54th Drive E, then continuing to Lena Road.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from  8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is early summer 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Installation of waterline under US 41 by boring under the road at the south east and south west corners. This activity is expected to last 3 weeks. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during day time only.
  • Installation of drainage structures at the SW corner of 10th Street is expected on Saturday, daytime.
  • Work is expected Monday night, May 13 and Tuesday night, May 14 at 10th Street. Crews are expected to pave the NW corner of 10th Street. Expect heavy equipment, trucks and rollers. Expect vibration from the rollers. Work is expected from 6 p.m. to 6 a.m.
  • A new traffic pattern on west side of 10th Street is expected starting Tuesday night. Travel lanes will be slightly shifted north. The new pattern will be well marked and signed.
  • Temporary single lane closures may occur between 9th Street and 15th Street from        9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the designated sidewalks and cross walks.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • East bound right turn lane at 10th Street will be closed until underground utilities complete in the area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, May 31. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is summer 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US  to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  118 Hits
0 Comments
118 Hits
  0 Comments
May
02

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF MAY 5, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit http://www.FL511.com  or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Manatee County rest area is closed for renovations. Motorists should use the Pinellas County rest area during this time. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275. Expected completion is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Expect nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning Monday, May 6 through Friday, May 10. Expect nighttime/overnight lane closures on the I-75 northbound ramp to I-275 northbound from 9 p.m. to 6 a.m. Tuesday, May 7. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining and noise walls, drainage improvements, working on the bridges over SR 70 and the Braden River, and SR 70 road work.

  • Crews are working on the interstate bridges over the Braden River.  Boaters are urged to exercise caution if they travel underneath the bridges.  Spotters will be watching for boaters to assist them through the work zone.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from  8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA., LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 301 from SR 780 (Fruitville Road) to 10th Street: Construction project: Crews are making median modifications, installing traffic separators, constructing turn-lanes, improving drainage, and constructing sidewalk. Expect nighttime/overnight lane closures from   8 p.m. to 7 a.m. Expected completion is late summer 2019. AJAX Paving Industries of Florida is the contractor.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • New traffic pattern was implemented on 14th Street going east and west. Pay close attention to barrels, pavement markings and traffic lights. Pedestrians need to cross at designated crosswalks and avoid work zones for safety reasons.
  • Installation of waterline under US 41 by boring under the road at the south east and south west corners. This activity is expected to last 3 weeks. There will be noise from boring equipment, excavators and pumps. Pumps are expected to run 24/7. Work currently is expected during day time only.
  • Removal of asphalt and old curb on the south east corner of 14th Street is expected. Expect noise from concrete and asphalt removal, construction equipment and dust.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Temporary disruption to access is expected while crews are setting up equipment trucks moving in and out of the work zones. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Concrete curbs are expected to be built at 10th Street. Expect concrete trucks entering and leaving the work zones.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Pedestrian crossings on 14th Street/Imperial Drive at US 41 have been reconfigured around the work zone. Pedestrians are advised to use the use designated sidewalks and cross walks.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Water main tie in procedures are scheduled along US 41. Expect construction vehicles throughout the day.
  • East bound right turn lane at 10th Street will be closed until underground utilities complete in the area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, May 31. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and James Street from 7 p.m. to 6 a.m. beginning Sunday, May 5 through Thursday, May 9.
  • Expect southbound nighttime lane closure on US 41 between Center Road and Via Veneto from 7 p.m. to 6 a.m. beginning Monday, May 6 through Friday, May 10.
  • Expect southbound nighttime lane closure on US 41 between Center Road and Via Veneto from 7 p.m. to 6 a.m. beginning Monday, May 13 through Friday, May 17. 

SR 776 (Indiana Avenue) at CR 777 (Dearborn Street): Construction project: Crews are making pedestrian and ADA improvements, vehicle detection overhead traffic signal modifications, sidewalk enhancements and installing highway lighting. Expect northbound lane closures from 7:30 p.m. to 7:30 a.m. and southbound lane closures from 8 p.m. to 7:30 a.m. Expected completion is summer 2019. Contact Network LLC is the contractor.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  138 Hits
0 Comments
138 Hits
  0 Comments
Apr
19

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF APRIL 21, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion.  There will be short nighttime, intermittent lane closures (45 minutes or less) on the inside lanes of northbound and southbound  I-275 and one short duration shoulder closure on southbound I-275 ahead of the ramp to the Manatee County Skyway Rest Area to add “CLOSED” placards to overhead signs. The Pinellas County Skyway Rest Area will reopen during the week of April 22, 2019 and the Manatee County Skyway Rest Area (south of the bridge) will close. During the Manatee Rest Area closure, motorists will be directed to the Pinellas County Skyway Rest Area. The closure is expected to last until spring 2020. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 will remain closed into the summer. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining and noise walls, drainage improvements, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8:45 p.m. to 6 a.m. (northbound) or 8 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Driveway, curb and sidewalk construction is expected on 14th Street on the east side of US 41. Temporary disruption to access is expected while crews are setting up equipment and pouring concrete. Access to properties is always maintained.
  • Grading of roadway base is expected at 10th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Concrete curbs are expected to be built at 10th Street. Expect concrete trucks entering and leaving the work zones.
  • Asphalt paving is expected at 14th Street/Imperial Drive at the end of the week. Expect lane closures with flaggers, asphalt trucks and vibration from the compaction equipment.
  • Traffic pattern change is scheduled on Imperial Drive and 14th Street on April 29th. Night work is expected on April 29th starting at 6 p.m. to 6 a.m. April 30th.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection. Pedestrian paths may also be rearranged to accommodate work in this area
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day. East bound right turn lane will be closed and will remain closed for 3 to 4 days.
  • Preparation for sidewalks along US 41 on the west side. Expect heavy equipment and concrete trucks.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of  US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, April 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, April 22 through Friday, April 26.
  • Expect a northbound and southbound nighttime traffic shift on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Wednesday, April 24 through Thursday, April 25.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

 

Continue reading
  160 Hits
0 Comments
160 Hits
  0 Comments
Apr
18

Sarasota Manatee Barrier Islands Traffic Study

barrierisland Barrier Island Traffic Study

Steering Committee Meeting April 23, 2019

Bartow, Fla. – FDOT will be holding the final steering committee meeting of the Barrier Islands Traffic Study at 9:30 a.m., Tuesday, April 23, 2019 at the CrossPointe Fellowship Church at 8605 Gulf Drive, Holmes Beach, Florida, 34217. The team is excited to be heading into Phase III of the Traffic Study.

Phase I involved reviewing prior studies for implementable ideas and Phase II looked at operational improvements. Phase I and Phase II have been finished and the recommendations finalized. Phase III will be looking more to the future – identifying mid to long term solutions.

The team believes the future focus should be on moving people, not solely on moving cars. To help accomplish this, the steering committee will be focusing on what the Vision for the Barrier Islands is. The goal of the FDOT team is to use this Vision to help guide suggestions and projects towards its realization. What does the community want to look like in the future?

FDOT and Stantec have included the suggestions made by the steering committee to ensure that the Island’s suggestions were incorporated and addressed.  Phase III Is scheduled to end in Fall 2019. The final Public Meeting is expected to be held in early 2020. This date will ensure that both full time and seasonal residents will have the opportunity to attend the meeting and participate. 

Persons who require special accommodations under the Americans with Disabilities Act (ADA) or people who require translation services (free of charge) should contact FDOT Project Manager Bessie Reina, by phone at (863)-519-2656 or by email at This email address is being protected from spambots. You need JavaScript enabled to view it. at least seven (7) days prior to the meeting. 

If you are hearing or speech impaired, please contact the Florida Department of Transportation using the Florida Relay Service, 1 (800) 955-8771 (TDD) or 1 (800) 955-8770 (Voice). 
FDOT solicits public participation without regard to race, color, national origin, age, sex, religion, disability, or family status.

###

Florida Department of Transportation
Innovative, Efficient and Exceptional

Continue reading
  616 Hits
0 Comments
616 Hits
  0 Comments
Apr
12

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF APRIL 14, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, April 14. caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, drainage improvements, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are working on punch-list items.

  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project. 

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is mid-2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

 

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Driveway, curb and sidewalk construction is expected on 14th Street on the east side of US 41. Temporary disruption to access is expected while crews are setting up equipment and pouring concrete. Access to properties is always maintained.
  • Finishing and fine grading of roadway base is expected on the west side of US 41 and at 14th Street. Expect noise from heavy machinery and dust with trucks moving in and out of traffic.
  • Permanent light poles are expected to be installed on the west side of US 41. Expect flat bed and bucket trucks moving in and out of the work zones.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection. Pedestrian paths may also be rearranged to accommodate work in this area
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day. East bound right turn lane will be closed and will remain closed for 3 to 4 days.
  • Preparation for sidewalks along US 41 on the west side. Expect heavy equipment and concrete trucks.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of       US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, April 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and      9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and James Street from 7 p.m. to 6 a.m. beginning Monday, April 15 through Wednesday, April 17.
  • Expect northbound and southbound nighttime lane closures on US 41 between Center Road and Gulf Coast Boulevard from 7 p.m. to 6 a.m. beginning Monday, April 22 through Friday, April 26.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  129 Hits
0 Comments
129 Hits
  0 Comments
Apr
09

Don't Forget to Wear Orange

go-orange Go Orange!

Go Orange Day on Wednesday, April 10!

As part of National Work Zone Awareness Week (April 8-12), FDOT encourages everyone to wear orange for Go Orange Day on Wednesday, April 10, as a visual reminder to others of work zones.

Feel free to post your photos on social media using the hashtags #GoOrangeDay and #WorkZoneSafety to further spread awareness of work zone safety.

While fun, participation in Go Orange Day and National Work Zone Awareness Week goes a long way in getting much-needed attention on work zone safety.

For tips on traveling safely in work zones, go to: http://bit.ly/2CKcGVQ

Continue reading
  156 Hits
0 Comments
156 Hits
  0 Comments
Apr
05

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF APRIL 7, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, April 7. caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, drainage improvements, constructing noise walls behind the Creekside community, and working on the bridges over SR 70 and the Braden River.

  • Motorists are advised that on Monday, April 8th, during the overnight hours from    11 p.m. to 5 a.m., the I-75 off-ramp to SR 70 eastbound and westbound will be closed, weather permitting.  Motorists are advised to go I-75 exit at Exit 220/SR 64 and use local routes; Exit 224/University Parkway and return to the interstate northbound and exit at SR 70; or, use local routes.
  • On Monday, April 8 through Friday, April 12, the SR 70 at Manor Hill Way/Twelve Oaks Plaza driveway intersection will be partially closed. Motorists will be able to enter the plaza from the driveway – use caution entering the driveway or use Tara Boulevard to Stone River Road; however, motorists must use 55th Avenue East to exit the plaza. The westbound SR 70 median opening for Twelve Oaks Plaza will be fully closed periodically between April 8th and April 12th. Motorists will need to enter from Tara Boulevard and Stone River Road; or, make a U-turn at Tara Boulevard and enter the plaza. Closures will be from 8 a.m. through evening hours.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.

Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction. Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently striping SR 64, installing sod, and working on punch-list items.

  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is mid-2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

Various locations along US 41, US 19 and SR 780: Construction project: Crews are installing highway lighting and constructing sidewalks at various locations along US 41, US 19 and SR 780 in Manatee and Sarasota Counties. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is summer 2019. The contractor is Highway Safety Devices, Inc.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Waterline tie in at 14th Street scheduled April 9th. Daytime operation expect heavy equipment, backup alarms and tight driving conditions.
  • Installation of roadway base is expected on the west side of US 41 and at 14th Street. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Contractor will be compacting the base with vibrating rollers. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction; the vibrations will be felt and noticeable in the vicinity. This operation is expected for approximately one week, weather permitting.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection. Pedestrian paths may also be rearranged to accommodate work in this area
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day. East bound right turn lane will be closed and will remain closed for 3 to 4 days.
  • Preparation for sidewalks along US 41 on the west side. Expect heavy equipment and concrete trucks.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of       US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, April 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Expect north and southbound nighttime lane closures on US 41 between Via Venato and Seaboard Avenue from 7 p.m. to 6 a.m. through Sunday, April 14. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

SR 72 at various locations: Construction project: Crews are installing highway lighting and constructing sidewalk along SR 72 at Frontage Road; Gantt Road; Honore Avenue; McIntosh Road; Sawyer Road; Beneva Road; Lockwood Ridge Road; Swift Road, Gateway Avenue, and at the Sarasota Pavilion entrance. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. Expected completion is late summer 2019. The contractor is Florida Safety Contractors, Inc.

Continue reading
  162 Hits
0 Comments
162 Hits
  0 Comments
Mar
28

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF MARCH 31, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, March 31. Motorists should also expect nighttime/overnight lane closures on the I-275 southbound to I-75 southbound ramp from 9 p.m. to 6 a.m. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, drainage improvements, constructing noise walls behind the Creekside community, and working on the bridges over SR 70 and the Braden River.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently striping SR 64 and the ramps, working on signalization and ITS, installing sod, and working on punch-list items.

  • Motorists are advised that on Monday, April 1st, during the overnight hours from    10 p.m. to 5 a.m., the SR 64 eastbound and westbound ramp to I-75 northbound will be closed, weather permitting.  Motorists are advised to go I-75 southbound to Exit 217/SR 70 and return to the interstate northbound; or, use local routes.
  • Motorists are advised that on Thursday, April 4th, during the overnight hours from  10 p.m. to 5 a.m., the I-75 southbound off-ramp to SR 64 will be closed, weather permitting.  Motorists are advised to exit at Exit 217/SR 70 and use local roads; or, exit at Exit 217/SR 70 and return to the interstate northbound; or, use local routes.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is mid-2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Possible night work on Thursday April 4th at 14th Street for a waterline tie in. Expect heavy equipment, backup alarms and lights. Work is expected starting around 7 p.m. to 6 a.m.
  • Installation of roadway base is expected on the west side of US 41 and at 14th Street. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Contractor will be compacting the base with vibrating rollers. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction; the vibrations will be felt and noticeable in the vicinity. This operation is expected for approximately two weeks, weather permitting.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day.
  • Crews will be working in the green zone of the Municipal Auditorium parking lot, use caution and watch for heavy equipment operating in the parking lot at the entrance from US 41.
  • Crews are expected to work on the box culvert at 10th Street. Pumps will be running 24/7 bypassing the box culvert into the bay.
  • Van Wezel Performing Arts Hall will be blocking off the concrete area between 10th Street and boat ramps for semi-trailers parking. This area will not be accessible to general public until the end of March.
  • Preparation for sidewalks and driveways and road base at the north east corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of       US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, April 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 (Venice Bypass) from Center Road from to Gulf Coast Boulevard: Construction project: Crews are widening US 41 from Center Road to Gulf Coast Boulevard to a six-lane highway; replacing traffic signals, installing new pavement markings and signage; installing concrete curb, sidewalks; improving new drainage, and installing new highway lighting. Expect north and southbound nighttime lane closures on US 41 between Via Venato and Seaboard Avenue from 7 p.m. to 6 a.m. through Sunday, April 7. Use caution and watch for changes in the traffic pattern. Bergeron Land Development, Inc. is the contractor. Expected completion is spring 2021.

Continue reading
  174 Hits
0 Comments
174 Hits
  0 Comments
Mar
21

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF MARCH 24, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, March 24. Motorists should also expect nighttime/overnight lane closures on the     I-275 southbound to I-75 southbound ramp from 9 p.m. to 6 a.m. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening I-75, the ramps, retaining walls, drainage improvements, constructing noise walls behind the Creekside community, and working on the bridges over SR 70 and the Braden River.

  • Motorists are advised that on Sunday, March 24th, during the overnight hours from 11 p.m. to 5 a.m., the SR 70 eastbound and westbound ramps to I-75 northbound will be closed, weather permitting.  Motorists are advised to go I-75 southbound to Exit 213/University Parkway and return to the interstate northbound; or, use local routes.
  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently paving and striping SR 64 and the ramps, installing sod, and completing drainage work.

  • Motorists are advised that on Wednesday, March 27th, during the overnight hours from 10 p.m. to 5 a.m., the SR 64 eastbound and westbound ramps to I-75 southbound will be closed, weather permitting.  Motorists are advised to go I-75 northbound to Exit 224/US 301 and return to the interstate southbound; or, use local routes.
  • Motorists are advised that on Thursday, March 28th, during the overnight hours from 10 p.m. to 5 a.m., the I-75 northbound off-ramp to SR 64 will be closed, weather permitting.  Motorists are advised to exit at Exit 217/SR 70 and use local roads; or, continue to Exit 224/US 301 and return to the interstate southbound; or, use local routes.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late 2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from      9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019..

SARASOTA COUNTY

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from    9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Installation of roadway base is expected on the west side of US 41 and at 14th Street. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Contractor will be compacting the base with vibrating rollers. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction; the vibrations will be felt and noticeable in the vicinity. This operation is expected for approximately two weeks, weather permitting.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day.
  • Crews will be working in the green zone of the Municipal Auditorium parking lot, use caution and watch for heavy equipment operating in the parking lot at the entrance from US 41.
  • Crews are expected to work on the box culvert at 10th Street. Pumps will be running 24/7 bypassing the box culvert into the bay.
  • Van Wezel Performing Arts Hall will be blocking off the concrete area between 10th Street and boat ramps for semi-trailers parking. This area will not be accessible to general public until the end of March.
  • Preparation for sidewalks and driveways and road base at the north east corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, March 29. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 from Waldemere Street to Arlington Street: Maintenance permit project: Crews are constructing a driveway. Expect nighttime/overnight southbound outside lane closures from 8 p.m. each night to 5 a.m. each morning through Friday, March 29. Use caution and expect possible delays.

Continue reading
  180 Hits
0 Comments
180 Hits
  0 Comments
Mar
18

Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF MARCH 17, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, March 17. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on the ramps, retaining walls, drainage improvements, constructing noise walls behind the Creekside community, and working on the bridges over SR 70 and the Braden River.  Crews will also be clearing vegetation behind the Tara Preserve community for upcoming noise wall construction.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently paving and striping SR 64, installing sod, performing ramp bridge work, and completing drainage work.

  • Motorists are advised that on Monday, March 18th, Tuesday, March 19th, and Wednesday, March 20th, during the overnight hours from 10 p.m. to 5 a.m., the SR 64 westbound ramp to I-75 southbound will be closed, weather permitting.  Motorists are advised to make a U-turn at 64th Street Ct E to use the southbound on-ramp.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late 2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

Business US 41 (9th Street W) at the Green Bridge; at 3rd Avenue W, and from 3rd Avenue W to SR 64 (Manatee Avenue): Construction project: Crews are constructing a multi-use path; constructing sidewalk; improving drainage; constructing turn lanes, and installing new signing and pavement markings. Expect nighttime/overnight lane closures on Business US 41 (9th Street W) from 8 p.m. to 6 a.m. while crews are working. Estimated completion is spring 2019. The contractor is Gosalia Concrete Constructors, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from 9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). The northbound outside lane will be closed from 32nd Avenue to 30th Avenue for approximately two weeks while crews complete drainage work. Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at   10th Street and 14th Street. Most of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from 9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Installation of roadway base is expected on the west side of US 41. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Contractor will be compacting the base with vibrating rollers. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction; the vibrations will be felt and noticeable in the vicinity. This operation is expected for approximately two weeks, weather permitting.
  • Curb installation is expected on the west side of US 41 from 14th Street to the boat ramp. Expect heavy equipment and concrete trucks going in and out of traffic.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day.
  • Crews will be working in the green zone of the Municipal Auditorium parking lot, use caution and watch for heavy equipment operating in the parking lot at the entrance from US 41.
  • Crews are expected to work on the box culvert at 10th Street. Pumps will be running 24/7 bypassing the box culvert into the bay.
  • Van Wezel Performing Arts Hall will be blocking off the concrete area between  10th Street and boat ramps for semi-trailers parking. This area will not be accessible to general public until the end of March.
  • Drainage structure and pipe installation along the west side of US 41 at the SW corner of 10th Street. Expect heavy equipment and trucks moving in and out of the travel lanes and parking lot for the Municipal Auditorium. Motorists are urged to use caution in the area. Expect equipment crossing 10th Street at the intersection.
  • Preparation for sidewalks and driveways and road base at the northeast corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, March 29. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 from Waldemere Street to Arlington Street: Maintenance permit project: Crews are constructing a driveway. Expect nighttime/overnight southbound outside lane closures from 8 p.m. each night to 5 a.m. each morning through Friday, March 22. Use caution and expect possible delays.

Continue reading
  135 Hits
0 Comments
135 Hits
  0 Comments
Mar
07

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch

FOR WEEK OF MARCH 10, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, March 10. Motorists should also expect nighttime/overnight lane closures on the I-275 southbound to I-75 southbound ramp from 9 p.m. to 6 a.m. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening the interstate, ramp work, constructing retaining walls, constructing noise walls, and working on drainage improvements. 

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently reconstructing SR 64, paving and striping, and completing drainage work.

  • Motorists are advised that on Sunday, March 10th, during the overnight hours from    11 p.m. to 5 a.m., the SR 64 eastbound and westbound ramps to I-75 southbound will be closed, weather permitting.  Motorists are advised to take I-75 north to Exit 224/US 301 and return onto the interstate southbound; or, to utilize local routes.
  • Motorists are advised that on Monday, March 11th, during the overnight hours from   11 p.m. to 5 a.m., the I-75 northbound off-ramp to SR 64 will be closed, weather permitting.  Motorists are advised to take Exit 217/SR 70 and use local routes; or, continue on I-75 north to Exit 224/US 301 and return onto the interstate southbound; or, to utilize local routes.
  • Motorists are advised that on Tuesday, March 12th, during the overnight hours from 11 p.m. to 5 a.m., the I-75 southbound off-ramp to SR 64 will be closed, weather permitting.  Motorists are advised to continue south to Exit 217/SR 70 and return to the interstate northbound; or, use local routes.
  • Motorists are advised that on Wednesday, March 13th, during the overnight hours from 11 p.m. to 5 a.m., the SR 64 on-ramps to I-75 northbound will be closed, weather permitting.  Motorists are advised to travel south on the interstate, take Exit 217/SR 70 and return to the interstate northbound; or, use local routes.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late 2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

Business US 41 (9th Street W) at the Green Bridge; at 3rd Avenue W, and from 3rd Avenue W to SR 64 (Manatee Avenue): Construction project: Crews are constructing a multi-use path; constructing sidewalk; improving drainage; constructing turn lanes, and installing new signing and pavement markings. Expect nighttime/overnight lane closures on Business US 41 (9th Street W) from 8 p.m. to 6 a.m. while crews are working. Estimated completion is spring 2019. The contractor is Gosalia Concrete Constructors, Inc.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from   9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch has been implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. The majority of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from 9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Installation of roadway base is expected on the west side of US 41. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Contractor will be compacting the base with vibrating rollers. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction; the vibrations will be felt and noticeable in the vicinity. This operation is expected for approximately one week depending on the weather.
  • Curb installation is expected on the west side of US 41 from 14th Street to the boat ramp. Expect heavy equipment and concrete trucks going in and out of traffic.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day.
  • Crews are expected to work on the box culvert at 10th Street. Pumps will be running 24/7 bypassing the box culvert into the bay.
  • Van Wezel Performing Arts Hall will be blocking off the concrete area between 10th Street and boat ramps for semi-trailers parking. This area will not be accessible to general public until the end of March.
  • New temporary entrance to the Municipal Auditorium is in place and open for traffic. New permanent entrance for the auditorium is expected to start. Access will always be maintained. Please exercise caution in the area and watch out for heavy equipment and workers in the area.
  • Drainage structure and pipe installation along the west side of US 41 at the SW corner of 10th Street. Expect heavy equipment and trucks moving in and out of the travel lanes and parking lot for the Municipal Auditorium. Motorists are urged to use caution in the area. Expect equipment crossing 10th Street at the intersection.
  • Preparation for sidewalks and driveways and road base at the northeast corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and vibrations due to compaction. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, March 29. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 from Waldemere Street to Arlington Street: Maintenance permit project: Crews are constructing a driveway. Expect nighttime/overnight southbound outside lane closures from 8 p.m. each night to 5 a.m. each morning through Friday, March 15. Use caution and expect possible delays.

Continue reading
  148 Hits
0 Comments
148 Hits
  0 Comments
Mar
01

Traffic Watch for Manatee and Sarasota Counties

traffic-watch Traffic Watch in Manatee and Sarasota Counties

FOR WEEK OF MARCH 3, 2019

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until spring 2019. The fishing piers will remain open during the closure. Construction is ongoing on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is spring 2020. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75. The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight southbound lane closures on I-75 the week of Sunday, March 3. Motorists should also expect nighttime/overnight lane closures on the I-275 southbound to I-75 southbound ramp from 9 p.m. to 6 a.m. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews will work on widening the interstate, ramp work, constructing retaining walls, constructing noise walls behind Creekside, clearing vegetation along Tara Preserve and River Place for noise walls, and working on drainage improvements. 

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8.45 p.m. to 6 a.m. (northbound) or 8.00 p.m. to 5 a.m. (southbound) through the duration of the construction.
  • Motorists should expect lane closures on SR 70 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.
  • Motorists should expect lane shifts on I-75 and SR 70 through the duration of the construction.
  • Drivers should exercise caution and be aware of construction vehicles entering and exiting the interstate through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Estimated completion is late 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64/Manatee Avenue Interchange (Exit 220): Construction project: This week, crews are currently: reconstructing SR 64, paving and striping, and completing drainage work.

  • Motorists are advised that on Tuesday, March 5th, during the overnight hours from 11 p.m. to 5 a.m., the I-75 northbound off-ramp to SR 64 will be closed, weather permitting.  Motorists are advised to take Exit 217/SR 70 and use local routes; or, continue on I-75 north to Exit 224/US 301 and return onto the interstate southbound; or, to utilize local routes.
  • Motorists are advised that on Friday, March 8th, during the overnight hours from 11 p.m. to 5 a.m., the SR 64 eastbound and westbound ramps to I-75 southbound will be closed, weather permitting.  Motorists are advised to take I-75 north to Exit 224/US 301 and return onto the interstate southbound; or, to utilize local routes.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late 2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

Business US 41 (9th Street W) at the Green Bridge; at 3rd Avenue W, and from 3rd Avenue W to SR 64 (Manatee Avenue): Construction project: Crews are constructing a multi-use path; constructing sidewalk; improving drainage; constructing turn lanes, and installing new signing and pavement markings. Expect nighttime/overnight lane closures on Business US 41 (9th Street W) from 8 p.m. to 6 a.m. while crews are working. Estimated completion is spring 2019. The contractor is Gosalia Concrete Constructors, Inc.

US 41 at Moccasin Wallow Road: Construction project: Crews are constructing turn lanes, resurfacing the roadway, improving drainage on Moccasin Wallow Road at US 41. Expect daytime and nighttime lane closures while construction is ongoing. Estimated completion is spring 2019. Blacktip Services Incorporated is the contractor.

US 41 from 301 Boulevard to 21st Avenue: Construction project: Crews are installing concrete traffic separators/directional turn-lanes within the median, resurfacing the roadway, improving drainage, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. and daytime lane closures from   9 a.m. to 4 p.m. (not within 600 feet of a signalized intersection). Expected completion is summer 2019. Blacktip Services Incorporated is the contractor.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed during construction. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

SR 64 at Rye Road: Construction project: Crews are constructing a multi-lane roundabout; resurfacing the roadway; improving drainage, and installing new highway lighting and landscaping. A traffic switch will be implemented shifting traffic to the current westbound lanes using temporary crossovers. Traffic will be reduced to one lane in each direction throughout the project limits. Rye Road will remain accessible during this time. The speed limit on State Road 64 will be reduced to 45 mph. Expect lane closures and a flagging operation at the SR 64 and Rye Road intersection on Saturday, March 2. Use caution and expect possible delays. IBT Construction is the contractor. Expected completion is late 2019.

SARASOTA COUNTY

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Crews are expected to work Saturday. Expect construction equipment and noise at 10th Street and 14th Street. The majority of the work is expected to occur at 10th Street and along US 41 from 10th Street to 14th Street on the west side.
  • Temporary single lane closures may occur between 9th Street and 15th Street from  9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • Installation of roadway base is expected on the west side of US 41. Expect noise from heavy machinery, dust and dump trucks moving in and out of traffic. Use extreme caution. Activity might be delayed due to rain.
  • Curb installation is expected on the west side of US 41 from 14th Street to the boat ramp. Expect heavy equipment and concrete trucks going in and out of traffic.
  • Sidewalk installation at 14th Street is expected on the NE and NW corner of the intersection.
  • Work on the permanent driveway for Centennial Park boat ramp off US 41. Driveway will always be accessible, but expect restricted areas while crews are working. Please pay close attention to flaggers and barricades in the area.
  • Installation of water main at the southwest corner of 10th Street and US 41. Expect construction vehicles with material crossing 10th Street throughout the day.
  • Crews are expected to work on the box culvert at 10th Street. Pumps will be running 24/7 bypassing the box culvert into the bay. Use caution at the intersection of 10th Street during a heavy storm event as there is a possibility of some street flooding.
  • Van Wezel Performing Arts Hall will be blocking off the concrete area between 10th Street and boat ramps for semi-trailers parking. This area will not be accessible to general public until the end of March.
  • New temporary entrance to the Municipal Auditorium is in place and open for traffic. New permanent entrance for the auditorium is expected to start. Access will always be maintained. Please exercise caution in the area and watch out for heavy equipment and workers in the area.
  • Drainage structure and pipe installation along the west side of US 41 at the SW corner of 10th Street. Expect heavy equipment and trucks moving in and out of the travel lanes and parking lot for the Municipal Auditorium. Motorists are urged to use caution in the area. Expect equipment crossing 10th Street at the intersection.
  • Preparation for sidewalks and driveways and road base at the north east corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and power tools. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Activities are subject to change due to adverse weather conditions and other schedule unforeseen problems. Other lane closures not yet scheduled may occur which do not appear on this update.

Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, March 29. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

US 41 from Waldemere Street to Arlington Street: Maintenance permit project: Crews are constructing a driveway. Expect nighttime/overnight southbound outside lane closures from 8 p.m. each night to 5 a.m. each morning through Friday, March 15. Use caution and expect possible delays.

Continue reading
  254 Hits
0 Comments
254 Hits
  0 Comments
We are committed to ensuring that this website is accessible to everyone under WAI-AA and US Section 508, making use of World Wide Web Consortium (W3C) standards. If you have any questions or suggestions regarding the accessibility of this site, please use our contact form.


Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public-records request, do not send electronic mail to this entity. Instead, contact this office by phone at 941-359-5772. Please note that our phone system can capture a voicemail as a recording, which if emailed may also be subject to a public-records request.