Traffic Watch for Manatee and Sarasota Counties

traffic-watch

FOR WEEK OF OCTOBER 21, 2018

Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones.
Remember, speeding fines are doubled in work zones.

As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to
learn about traffic conditions on major roadways across the state.
If you know before you go, you can plan accordingly and save time and money.

 

MANATEE COUNTY

I-275 at the Sunshine Skyway Rest Areas in Manatee and Pinellas Counties: Construction project: Improvements include constructing new rest areas and new parking lots with LED lighting, seawall repairs and extending the seawall at the Manatee County rest area to accommodate a new picnic pavilion. The Pinellas County Skyway Rest Area is closed for renovations. During this time, motorists will be directed to the Manatee County Skyway Rest Area. The closure is expected to last until fall 2018. The fishing piers will remain open during the closure. Construction is on-going on the new rest area site and the seawall on the Manatee side, west of I-275.  Expected completion of both rest areas is fall 2019. David Nelson Construction Company is the contractor. 

I-275 Southbound Ramp to I-75 Northbound (Exit 228): Construction project: Crews are replacing the concrete bridge deck on the southbound I-275 ramp to northbound I-75.  The I-275 southbound ramp to northbound I-75 is closed for approximately ten (10) months. Traffic is being detoured north on US 41/S Tamiami Trail to SR 674/E College Avenue in Hillsborough County. A temporary traffic signal has been installed on US 41 at the southbound I-275 exit. Periodic nighttime/overnight I-75 northbound/southbound and I-275 southbound lane closures beneath I-275 will occur during construction. There will be nighttime/overnight lane closures on the I-275 southbound ramp to I-75 southbound from 9 p.m. each night to 6 a.m. each morning the week of Sunday, October 21. Motorists should also expect nighttime/overnight southbound and northbound double lane closures on I-75 the week of Sunday, October 21, as needed. Use caution and watch for changes in the traffic pattern. Expected completion is summer 2019. Cone & Graham, Inc. is the contractor.

I-75 at SR 70 Interchange (Exit 217): Construction project: This week, crews are installing erosion control devices, clearing vegetation, setting up Maintenance of Traffic, and resurfacing I-75 northbound.

  • Motorists should expect lane closures on I-75 during nighttime/overnight hours from 8 p.m. to 5 a.m. through the duration of the construction.

Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late of 2021. The contractor is Sacyr Construction USA, LLC.

I-75 at SR 64 (Manatee Avenue) Interchange (Exit 220): Construction project: This week, crews are currently widening northbound and southbound I-75 and performing ramp, grading, utility, and drainage work, and SR 64 westbound reconstruction.

  • Motorists are advised that SR 64 will be paved during the overnight hours from 8 p.m. to 5 a.m. and will require traffic on SR 64 to shift a lane.
  • Motorists are advised that one lane closure in each direction on SR 64 may occur during the overnight hours between 8 p.m. and 5 a.m.
  • Motorists are advised that one lane closure in each direction on I-75 may occur during the overnight hours between 8 p.m. and 5 a.m. throughout the duration of the project.

This project reconstructs the interchange, widens interchange ramps and SR 64, and installs sidewalks and bicycle lanes on SR 64. Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in this area. Estimated completion is late 2019. The contractor is Prince Contracting LLC.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 301 from CR 675 to Moccasin Wallow Road: Construction project: Crews are installing new landscaping, irrigation and welcome signs. Superior Landscaping & Lawn Services is the contractor. Expected completion is fall 2018.

US 301 at Ellenton Gillette Road: Maintenance permit project: Crews are constructing a turn-lane. Expect daytime lane closures from 9 a.m. to 3:30 p.m. through Thursday, October 25. Use caution and expect possible delays.

Business US 41 (9th Street W) at the Green Bridge; at 3rd Avenue W, and from 3rd Avenue W to SR 64 (Manatee Avenue): Construction project: Crews are constructing a multi-use path; constructing sidewalk; improving drainage; constructing turn lanes, and installing new signing and pavement markings. Expect nighttime/overnight lane closures on Business US 41 (9th Street W) from 8 p.m. to 6 a.m. while crews are working. The outside southbound lane on Business US 41 over the Green Bridge is closed to traffic while the contractor is working on the concrete barrier wall. For safety purposes, the lane will remain closed 24/7 for approximately two months. Please plan additional travel time. Estimated completion is spring 2019. The contractor is Gosalia Concrete Constructors, Inc.

US 41 between 37th Avenue W and 36th Avenue W: Maintenance permit project: Crews are constructing a driveway. Expect intermittent northbound lane closures from 9 a.m. to  4 p.m. through Friday, October 26. Use caution and expect possible delays.

US 41 at 57th Avenue W: Maintenance permit project: Crews are constructing a driveway. Expect daytime lane closures from 9 a.m. to 3:30 p.m. through Thursday, October 25. Use caution and expect possible delays.

SR 789/Gulf Drive from SR 64 (Manatee Avenue) to SR 684 (Cortez Road): Maintenance permit project: Manatee County is installing new force mains and water mains. For additional information about the project, please visit the project website at www.amipipereplacement.com. 

SR 70 (15th Street E) at 9th Avenue E: Construction project: Crews are constructing a roundabout; installing highway lighting and landscaping; improving drainage; constructing sidewalk, and resurfacing the roadway. The intersection of SR 70 (15th Street E) and 9th Avenue E is closed to traffic for approximately six (6) months. Please use 13th Avenue E and 7th Avenue E as alternate routes during this time. A temporary traffic signal will be installed at the intersection of SR 70 (15th Street E) and 13th Avenue E while the detour is in effect. Watson Civil Construction, Inc., is the contractor. Expected completion is spring 2019.

 

SARASOTA COUNTY

Laurel Road at the Legacy Trail Crossing: Construction project: Crews are constructing a pedestrian bridge along the Legacy Trail over Laurel Road. Please be aware of construction vehicles entering and leaving the construction zone. Both northbound and southbound trail traffic are now being detoured to the west along the signed detour route. Both sidewalks on the north and south side of Laurel Road are now closed. Please follow detour signs provided. Intermittent single lane closures at the bridge can be expected from 9 a.m. to 3 p.m. weekdays only. Overnight full road closures on Laurel Road with detours are being scheduled for the week of October 29th. Denson Construction, Inc. is the contractor for the bridge. Expected completion is late 2018.

I-75 at the University Parkway Interchange (Exit 213): Construction project: Crews are installing landscaping and irrigation systems at the I-75 and University Parkway interchange. Lane closures on I-75, if needed, will occur between 8 p.m. and 5 a.m. Lane closures on University Parkway, if needed, will occur between 9 p.m. and 6 a.m. Estimated completion is spring 2019. The contractor is Frankie Valdez Company, Inc.

US 41 from SR 789 to Ritz Carlton Drive and sidewalk located along the north side of SR 789 from Sunset Drive to US 41: Maintenance permit project: The sidewalk will remain closed until construction of the development located at the corner of US 41 and SR 789 is complete. Pedestrians should follow the established detour.

US 41 from Salford Boulevard to Sumter Boulevard: Construction project: Crews are widening US 41 from Salford Boulevard to Sumter Boulevard to a six-lane highway; resurfacing the roadway; improving drainage; constructing sidewalk, and installing highway lighting. Expect nighttime/overnight lane closures from 8:30 p.m. to 5:30 a.m. when crews are resurfacing the roadway. Expect periodic driveway closures along the northbound lanes while crews are installing drainage systems. Russell Engineering, Inc. is the contractor. Expected completion is spring 2019.

US 41 Roundabouts at 10th Street and 14th Street, Sarasota:  Construction project: Crews continue work within the right-of-way, medians and driveways.

  • Temporary single lane closures may occur between 9th Street and 15th Street from 9 a.m. to 4 p.m. and between 7 p.m. and 6 a.m. if nighttime activities are scheduled.
  • 10th Street, west side of US 41 is open for traffic. However, there may be intermittent lane closures as crews work to install waterline along 10th Street while traffic is directed with the help of flaggers.
  • Grading and new driveway installations on the east side of US 41 on 14th Street is scheduled in a couple of weeks. Individual home owners impacted by these activities will be contacted to coordinate.
  • Installation of concrete traffic railing is expected at Hog Creek, northwest side of US 41 and 11th Street. Watch for heavy equipment and concrete trucks moving in and out of travel lanes.
  • Drainage structure and pipe installation is expected along the west side of US 41 between Hog Creek and 14th Street. Expect heavy equipment and trucks moving in and out of the travel lanes. Motorists are urged to use caution in the area.
  • Light pole base foundations and preparation for sidewalks and driveways and road base are scheduled for the north east corner of 14th Street and US 41 intersection. Expect heavy equipment, concrete and dump trucks and power tools. Pedestrian paths may also be rearranged to accommodate work in this area.
  • Installation of waterline across US 41 at 10th Street is complete. Activity in the area will be for waterline testing prior to activation. All work is expected during the day time. The contractor’s work zone for this operation will be in the median of 10th Street east of US 41. Motorists are urged to use caution and be mindful of the workers and the heavy equipment moving in and out of this area.
  • West bound 10th Street will have restricted lanes on the east side of US 41, only 2 lanes will be available to make left turns, through traffic and right turns. Heavy equipment will be staged in the median, with large trucks moving in and out of the median. Motorists are urged to use caution in the area.
  • Centennial Park Boat Ramp driveway on 10th Street will be closed. Motorists can access the boat ramp via the US 41 entrance. Northbound left turn lane from US 41 into the boat ramp is available.
  • Pedestrian paths have been reconfigured around the work zone, please use designated sidewalks and cross walks. No pedestrian access on the west side of US 41 beyond Centennial Park, pedestrians are advised to use the sidewalk on the east side of US 41. Impacts to pedestrian access south of the Centennial Park on the west side of US 41 is expected while the contractor is performing excavation in the area.
  • Box culvert construction is ongoing. Contractor will be preparing for the demolition and installation of the next sections of the box culvert. Expect noise from concrete saws and jack hammers. There will be pumps running 24/7 for dewatering in the area. This is an active construction zone and for safety purposes only authorized personnel are allowed inside the work zone.
  • The traffic pattern will be limited to right turn in/out for 11th, 12th and 13th Street. Traveling southbound and northbound direction left turns are not permitted at 11th, 12th, 13th and 14th Streets. Motorists are advised to follow the posted signs.
  • Temporary detour route in effect. Use Cocoanut Avenue as alternate route to access 12th, 13th, 14th and 15th Street. Motorists are advised to follow the posted detour route and seek an alternate route while traveling in this area.
  • Speed limit is reduced to 30 mph. Speeding fines are doubled in the construction area when workers are present.

Improvements being made as part of this project consist of reconstructing the signalized intersections and replacing them with roundabouts, enhancing connectivity, circulation and safety. US 41 will be widened between the two intersections and will include bike lanes as well as dedicated turn lanes, a 10-foot sidewalk along the west side, and a 6-foot sidewalk along the east side. Other improvements include raised islands for pedestrian refuge at the intersections of US 41 at 10th Street and 14th Street, pedestrian signals, LED street lights, landscaping, and City of Sarasota utility and underground drainage structure replacements. Expected completion is spring 2020. The contractor is IBT Construction LLC.

US 41 from Hospital Road to River Road: Maintenance permit project: Crews are constructing new turn-lanes, driveway connections, and working in the medians. Expect intermittent north and southbound daytime lane closures from 9 a.m. to 4:30 p.m. through Friday, October 26. Use caution and expect possible delays.

US 41 from McIntosh Road to Beneva Road: Construction project: Crews are constructing sidewalk and bicycle lanes, improving drainage, reconstructing the US 41 southbound bridge over Catfish Creek south of Central Sarasota Parkway, installing highway lighting, upgrading signals, and installing new signing and pavement markings.

  • TRAFFIC SWITCH – Southbound US 41 traffic is reduced to one lane and shifted into one of the northbound lanes while construction is underway on the southbound Catfish Creek Bridge. Northbound US 41 will also be reduced to one lane to accommodate southbound traffic. This traffic pattern will be in effect for approximately five (5) months. Use caution and plan additional travel time.
  • Northbound nighttime/overnight lane closures may occur between 6 p.m. and 6 a.m.
  • Southbound nighttime/overnight lane closures may occur between 6:30 p.m. and 9:30 a.m.
  • The speed limit is reduced to 45 mph within the construction zone.

Motorists should use caution and obey the posted speed limit. Expected completion is fall 2019. The contractor is Morrison-Cobalt JV.

US 41 from Tuscola Boulevard to Ortiz Boulevard: Construction project: Crews are constructing a multi-use path; installing bus pads and shelters; improving drainage; constructing/replacing sidewalk; installing guardrail and highway lighting, and installing new signing and pavement markings. Expect nighttime/overnight lane closures from 7 p.m. to 6 a.m. Daytime lane closures between 9 a.m. and 2 p.m. are possible. Lane closures within 600 feet of signalized intersections are not permitted between 5:30 a.m. and 7 p.m. Florida Safety Contractors, Inc. is the contractor. Expected completion is spring 2019. 

SR 758 at the Siesta Drawbridge: Bridge maintenance project: Crews are working on the bridge. Expect nighttime/overnight east and westbound lane closures, controlled by flaggers, from 9 p.m. to 5 a.m. Wednesday, October 24. Use caution and expect possible delays.

SR 72 at Gateway Road: Construction project: This project is to replacing existing crosswalks, crosswalk landings, pedestrian signals, and lighting.  This week, crews will work on site cleanup and punch list items.

  • Drivers should anticipate lane closures; however, lane closures will be prohibited during peak hours from 6 a.m. to 9 a.m. and 4 p.m. to 7 p.m.

Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in the work zone. Estimated completion is fall 2018, weather permitting. Ajax Paving Industries of Florida, LLC is the contractor.

SR 72 at Swift Road and Beneva Road: Construction project: This project is to replacing existing crosswalks, crosswalk landings, and pedestrian signals.  This week, crews will work on site cleanup and punch list items.

  • Drivers should anticipate lane closures; however, lane closures will be prohibited during peak hours from 6 a.m. to 9 a.m. and 4 p.m. to 7 p.m.

Variable message signs will be in place to alert drivers that work is underway. Drivers should use caution while traveling in the work zone. Estimated completion is summer 2018, weather permitting. Ajax Paving Industries of Florida, LLC is the contractor.

 

www.mympo.org | @saramanampo | This email address is being protected from spambots. You need JavaScript enabled to view it.

Traffic Watch for Manatee and Sarasota Counties